22928 W INGOMAR ST 91304

Certificate Information: 22928 W INGOMAR ST 91304

Application / Permit
22010-20000-03139
Plan Check / Job No.
B22VN09811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23'-6" x 52'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
Permit Issued
Issued on 10/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2022 APPLICANT
Assigned to Plan Check Engineer 6/27/2022 ARTIN ZARUKIAN
Corrections Issued 6/28/2022 ARTIN ZARUKIAN
Building Plans Picked Up 6/30/2022 APPLICANT
Issued 10/17/2022 APPLICANT
CofO in Progress 4/3/2023 KRISTEN BEVERIDGE
Permit Finaled 4/21/2023 JOHN JANSON
CofO Issued 4/21/2023 JOHN JANSON
Permit Finaled 4/21/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/1/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/1/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/1/2022 LEE GUILBEAUX
Sewer availability Cleared 7/1/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/1/2022 LEE GUILBEAUX
Construction near power lines Cleared 9/7/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 10/7/2022 RUEL COLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/28/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/28/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 10/28/2022 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/2/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 11/2/2022 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/2/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 12/2/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 12/2/2022 Approved CHRIS CHRISTENSEN
Wood Frame 12/2/2022 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 12/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 12/7/2022 Partial Approval CHRIS CHRISTENSEN
Wood Frame 12/7/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 12/9/2022 No Access for Inspection KRISTEN CAUSEY
Rough-Elec/Plmb/HVAC 12/9/2022 No Access for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 12/12/2022 Conditional Approval KRISTEN CAUSEY
ELECTRICAL-Rough 12/12/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/12/2022 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 12/16/2022 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 12/16/2022 Approved JUSTIN HAWLEY
Green Building Rough 12/16/2022 Approved JUSTIN HAWLEY
Insulation 12/16/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/16/2022 Partial Approval JUSTIN HAWLEY
Verify Sprinkler Sign Off 12/16/2022 Approved JUSTIN HAWLEY
Drywall Nailing 12/19/2022 No Access for Inspection KRISTEN CAUSEY
Green Building Rough 12/19/2022 No Access for Inspection KRISTEN CAUSEY
Insulation 12/19/2022 No Access for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 12/28/2022 Not Ready for Inspection KRISTEN CAUSEY
Shower Pan 12/28/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 1/6/2023 Approved KRISTEN CAUSEY
Underground Mechanical 1/23/2023 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Final 2/14/2023 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 3/1/2023 Approved KRISTEN CAUSEY
Drywall Nailing 3/1/2023 Approved KRISTEN CAUSEY
Final 3/1/2023 Corrections Issued KRISTEN CAUSEY
Footing/Foundation/Slab 3/1/2023 Approved KRISTEN CAUSEY
Green Building Final 3/1/2023 Approved KRISTEN CAUSEY
Green Building Rough 3/1/2023 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Not Ready KRISTEN CAUSEY
Service/Power Release 3/1/2023 Not Ready for Inspection KRISTEN CAUSEY
Smoke Detectors 3/1/2023 Approved KRISTEN CAUSEY
ELECTRICAL-Final 3/20/2023 Corrections Issued HENRY KIM
Final 3/20/2023 Corrections Issued HENRY KIM
Gas Test 3/20/2023 Corrections Issued HENRY KIM
HVAC-Final 3/20/2023 Corrections Issued HENRY KIM
PLUMBING-Final 3/20/2023 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Not Ready HENRY KIM
ELECTRICAL-Final 3/31/2023 Approved KRISTEN CAUSEY
Final 3/31/2023 OK to Issue CofO KRISTEN CAUSEY
HVAC-Final 3/31/2023 Approved KRISTEN CAUSEY
PLUMBING-Final 3/31/2023 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved KRISTEN CAUSEY
Service/Power Release 3/31/2023 Approved KRISTEN CAUSEY