8414-8414 1/2 S WILEY POST AVE 90045
Certificate Information: 8414-8414 1/2 S WILEY POST AVE 90045
- Application / Permit
- 22010-20000-03118
- Plan Check / Job No.
- B22VN09743
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (2) DETACHED ONE STORY ADU. SEE COMMENT.
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | TSE MING HUANG |
| Corrections Issued | 8/8/2022 | TSE MING HUANG |
| Quality Review Completed | 8/11/2022 | KEN GILL |
| Building Plans Picked Up | 8/23/2022 | APPLICANT |
| Plan Check Approved | 6/2/2023 | TSE MING HUANG |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 7/15/2025 | DAVID FEILER |
| Permit Finaled | 7/18/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/18/2025 | RICHARD STEINBACH |
| CofO Issued | 7/18/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/19/2022 | JENSON LEE |
| Construction near power lines | Cleared | 10/24/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/24/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 11/10/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 3/14/2023 | SARAH YOUSSEF |
| Address approval | Cleared | 3/22/2023 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 3/22/2023 | JENSON LEE |
| Tenant Habitability Plan | Cleared | 3/30/2023 | ISMAEL HERNANDEZ |
| Specific Plan | Cleared | 4/25/2023 | EDUARDO HERMOSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/24/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 5/29/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 6/17/2024 | Approved | BOBBY KEY |
| Deputy Wood Construction | 8/14/2024 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 8/28/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/28/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/13/2024 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 9/13/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 9/13/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/13/2024 | Partial Approval | BOBBY KEY |
| Insulation | 10/7/2024 | Approved | DAVID FEILER |
| Shower Pan | 10/7/2024 | Partial Approval | DAVID FEILER |
| Shower Pan | 10/10/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 10/16/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/16/2024 | Approved | BOBBY KEY |
| Pre-Inspection | 1/16/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Underground Mechanical | 1/21/2025 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Final | 5/28/2025 | Not Ready for Inspection | JESUS PINEDA |
| Final | 5/28/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 5/28/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 5/28/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 5/28/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | JESUS PINEDA |
| Service/Power Release | 5/28/2025 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 5/28/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 7/9/2025 | Approved | ANTHONY EGSON |
| Final | 7/9/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 7/9/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 7/9/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2025 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 7/9/2025 | Approved | ANTHONY EGSON |
| Final | 7/15/2025 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 7/15/2025 | Approved | DAVID FEILER |