NEW 62'6" X 38' TWO STORY SFD WITH ATTACHED TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQURIED, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/21/2023
Issuing Office
Current Status
CofO Issued on 1/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 RARES BODEA
Corrections Issued 7/5/2022 RARES BODEA
Quality Review Completed 7/14/2022 STEVEN KIM
Building Plans Picked Up 7/15/2022 APPLICANT
Applicant returned to address corrections 3/13/2023 RARES BODEA
Plan Check Approved 3/17/2023 RARES BODEA
Issued 3/21/2023 APPLICANT
CofO in Progress 12/19/2023 MISAEL ESPARZA
Permit Finaled 1/31/2024 RUBEN SALAS
CofO Issued 1/31/2024 RUBEN SALAS
Permit Finaled 1/31/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 8/4/2022 MITESH PATEL
Hydrant and Access approval Cleared 8/25/2022 RUEL COLE
Address approval Cleared 9/2/2022 JOSE DUARTE-DIAZ
Permit Cleared 9/2/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 9/2/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 9/6/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 9/6/2022 JOSE DUARTE-DIAZ
Trees in Parkway Cleared 2/22/2023 ADALBERTO VERA
ZI Cleared 3/2/2023 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/27/2023 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 5/5/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 5/30/2023 Approved JOHN COLEMAN
Footing/Foundation/Slab 5/30/2023 Approved JOHN COLEMAN
Deputy Wood Construction 6/6/2023 Conditional Approval MICHAEL SMITH
Deputy Reinf. Concrete 6/7/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval JOHN COLEMAN
Deputy Steel/Welding 7/5/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Corrections Issued THOMAS FINNILA
HVAC-Rough 7/19/2023 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 7/19/2023 Approved THOMAS FINNILA
ELECTRICAL-Rough 7/31/2023 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/3/2023 Approved MISAEL ESPARZA
Deputy Wood Construction 8/3/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 8/3/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Approved MISAEL ESPARZA
Green Building Rough 8/3/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 8/3/2023 Approved MISAEL ESPARZA
Shower Pan 8/3/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 8/3/2023 Approved MISAEL ESPARZA
Insulation 8/8/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/8/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 8/14/2023 Approved MISAEL ESPARZA
Green Building Rough 8/14/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/14/2023 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Final 11/21/2023 Corrections Issued MISAEL ESPARZA
Final 11/21/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 11/21/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 11/21/2023 Corrections Issued MISAEL ESPARZA
MERV13>=Final 11/21/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 11/21/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 11/21/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/21/2023 Approved MISAEL ESPARZA
Final 11/30/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 11/30/2023 Approved CHRISTOPHER ROJAS
MERV13>=Final 11/30/2023 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 11/30/2023 Approved CHRISTOPHER ROJAS
Final 12/18/2023 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 1/16/2024 Approved MISAEL ESPARZA