5834 1/2 N CORBIN AVE 91356
Certificate Information: 5834 1/2 N CORBIN AVE 91356
- Application / Permit
- 22010-20000-03094
- Plan Check / Job No.
- B22VN09617
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SECOND DWELLING UNIT WITH ATTACHED STORAGE AND COVERED PATIO PER SB9. WORK PER ENGINEER. NFPA 13R FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 4/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2022 | ROSENDO MEDINA |
| Corrections Issued | 6/25/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Applicant returned to address corrections | 3/15/2024 | ROSENDO MEDINA |
| Application Withdrawn-Void | 3/29/2024 | JEROME MAGAT PALMA |
| Re-Activate Application | 3/29/2024 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/16/2024 | ROSENDO MEDINA |
| Issued | 4/16/2024 | APPLICANT |
| CofO in Progress | 11/4/2025 | JON MCHUGH |
| Permit Finaled | 11/14/2025 | JOHN JANSON |
| CofO Issued | 11/14/2025 | JOHN JANSON |
| Permit Finaled | 11/14/2025 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/5/2024 | SAMUEL LINN |
| Address approval | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/11/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2024 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 3/28/2024 | MAX LODER |
| Senate Bill 9 | Cleared | 3/28/2024 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 4/12/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2024 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 4/19/2024 | Corrections Issued | JON MCHUGH |
| Deputy Steel/Welding | 4/24/2024 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 4/24/2024 | Approved | JON MCHUGH |
| Underground Mechanical | 4/24/2024 | Partial Approval | JON MCHUGH |
| Deputy Steel/Welding | 4/30/2024 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 5/8/2024 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 5/8/2024 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 5/8/2024 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Partial Approval | MORRIS JACKSON |
| Deputy Wood Construction | 5/15/2024 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2024 | Approved | JON MCHUGH |
| Wood Frame | 5/29/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 6/5/2024 | Approved | MORRIS JACKSON |
| HVAC-Rough | 6/5/2024 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 6/5/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/6/2024 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 6/13/2024 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 6/24/2024 | Approved | JON MCHUGH |
| Green Building Rough | 6/24/2024 | Approved | JON MCHUGH |
| Insulation | 6/24/2024 | Conditional Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 6/24/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 7/30/2024 | Approved | JON MCHUGH |
| Final | 9/5/2025 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 9/5/2025 | Approved | ROBERT GOLD |
| Service/Power Release | 9/5/2025 | Not Ready for Inspection | ROBERT GOLD |
| Smoke Detectors | 9/5/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 10/16/2025 | SGSOV Not Ready | JON MCHUGH |
| Final | 10/23/2025 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 10/23/2025 | Not Required | JON MCHUGH |
| ELECTRICAL-Final | 11/4/2025 | Approved | JON MCHUGH |
| Final | 11/4/2025 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 11/4/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 11/4/2025 | Approved | JON MCHUGH |