12950 N FELLOWS AVE 91342

Certificate Information: 12950 N FELLOWS AVE 91342

Application / Permit
22010-20000-03086
Plan Check / Job No.
B22VN09581
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW 977 SQ.FT. DETACHED ADU AS PER WFPP ADU CHECKED per LAMC 12.22 A.22(C) AND (D)
Permit Issued
Issued on 12/8/2022
Issuing Office
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2022 APPLICANT
Assigned to Plan Check Engineer 6/28/2022 SUNMIN LEE
Corrections Issued 6/29/2022 SUNMIN LEE
Applicant returned to address corrections 8/8/2022 SUNMIN LEE
Applicant returned to address corrections 10/21/2022 SUNMIN LEE
Plan Check Approved 11/29/2022 SUNMIN LEE
Issued 12/8/2022 APPLICANT
CofO in Progress 11/22/2023 KEVIN BERBERYAN
Permit Finaled 2/14/2024 RUBEN SALAS
CofO Issued 2/14/2024 RUBEN SALAS
Permit Finaled 2/14/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/13/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/14/2022 MEGAN GODINEZ
Sewer availability Cleared 7/14/2022 MEGAN GODINEZ
Low Impact Development Cleared 10/12/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/28/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Mario Alberto; Lic. No.: C89006 43023 40TH ST WEST      LANCASTER, CA 93536

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/26/2023 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 2/3/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 3/23/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 3/23/2023 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 3/23/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/23/2023 Corrections Issued ARAM AVEDISIAN
Underground Mechanical 3/23/2023 Partial Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 3/23/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 3/30/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/30/2023 Approved ARAM AVEDISIAN
Wood Frame 3/30/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 4/5/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 4/5/2023 Partial Approval ARAM AVEDISIAN
Insulation 4/13/2023 Approved ARAM AVEDISIAN
Drywall Nailing 4/21/2023 Approved ARAM AVEDISIAN
Sewer 4/21/2023 Approved ARAM AVEDISIAN
Shower Pan 4/21/2023 Approved ARAM AVEDISIAN
Underground Mechanical 5/12/2023 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 6/1/2023 Partial Approval ARAM AVEDISIAN
Final 10/11/2023 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 10/11/2023 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 10/11/2023 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 10/11/2023 Approved KEVIN BERBERYAN
Final 11/9/2023 Conditional Approval KEVIN BERBERYAN
Footing/Foundation/Slab 11/9/2023 Approved KEVIN BERBERYAN
Service/Power Release 11/9/2023 Approved KEVIN BERBERYAN
Final 11/21/2023 OK to Issue CofO KEVIN BERBERYAN