12950 N FELLOWS AVE 91342
Certificate Information: 12950 N FELLOWS AVE 91342
- Application / Permit
- 22010-20000-03086
- Plan Check / Job No.
- B22VN09581
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 977 SQ.FT. DETACHED ADU AS PER WFPP ADU CHECKED per LAMC 12.22 A.22(C) AND (D)
- Permit Issued
- Issued on 12/8/2022
- Issuing Office
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2022 | SUNMIN LEE |
| Corrections Issued | 6/29/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 8/8/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 10/21/2022 | SUNMIN LEE |
| Plan Check Approved | 11/29/2022 | SUNMIN LEE |
| Issued | 12/8/2022 | APPLICANT |
| CofO in Progress | 11/22/2023 | KEVIN BERBERYAN |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
| CofO Issued | 2/14/2024 | RUBEN SALAS |
| Permit Finaled | 2/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/14/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 10/12/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/28/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Mario Alberto; Lic. No.: C89006 | 43023 40TH ST WEST LANCASTER, CA 93536 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/26/2023 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/23/2023 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/23/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 3/23/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/23/2023 | Corrections Issued | ARAM AVEDISIAN |
| Underground Mechanical | 3/23/2023 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 3/23/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/30/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/30/2023 | Approved | ARAM AVEDISIAN |
| Wood Frame | 3/30/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 4/13/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 4/21/2023 | Approved | ARAM AVEDISIAN |
| Sewer | 4/21/2023 | Approved | ARAM AVEDISIAN |
| Shower Pan | 4/21/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 5/12/2023 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/1/2023 | Partial Approval | ARAM AVEDISIAN |
| Final | 10/11/2023 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 10/11/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 10/11/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 10/11/2023 | Approved | KEVIN BERBERYAN |
| Final | 11/9/2023 | Conditional Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 11/9/2023 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 11/9/2023 | Approved | KEVIN BERBERYAN |
| Final | 11/21/2023 | OK to Issue CofO | KEVIN BERBERYAN |