13050 W TERRA BELLA ST 91331

Certificate Information: 13050 W TERRA BELLA ST 91331

Application / Permit
22010-20000-03082
Plan Check / Job No.
B22VN09580
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 40' X 30' ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
Permit Issued
Issued on 7/7/2023
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/26/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/29/2022 OMID HEDAYAT
Applicant returned to address corrections 11/30/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/17/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/25/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/11/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/20/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/29/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 7/3/2023 SEWADA ZADOORAN MILAGARDI
Issued 7/7/2023 APPLICANT
CofO in Progress 1/30/2026 MICHEL ABAJAN
Permit Finaled 2/20/2026 RUBEN SALAS
CofO Issued 2/20/2026 RUBEN SALAS
Permit Finaled 2/20/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/11/2022 CARLOS AGUILERA
Clean Up Green Up Cleared 8/11/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 8/17/2022 CARLOS AGUILERA
Sewer availability Cleared 8/17/2022 CARLOS AGUILERA
Low Impact Development Cleared 2/9/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 2/9/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/3/2025 Corrections Issued MICHEL ABAJAN
Pre-Inspection 2/3/2025 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/13/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 5/13/2025 Approved MICHEL ABAJAN
METHANE-Barrier 5/13/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 5/13/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 7/22/2025 Approved MICHEL ABAJAN
HVAC-Rough 7/22/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 7/22/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/4/2025 Approved MICHEL ABAJAN
Gas Test 8/4/2025 Not Ready for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 8/4/2025 Approved MICHEL ABAJAN
Gas Test 8/6/2025 Approved MICHEL ABAJAN
Sewer 8/6/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/19/2025 Not Ready for Inspection MICHEL ABAJAN
Insulation 8/22/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/22/2025 Approved MICHEL ABAJAN
Drywall Nailing 8/26/2025 Approved MICHEL ABAJAN
Shower Pan 8/26/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/31/2025 Approved MICHEL ABAJAN
Final 10/31/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 10/31/2025 Approved MICHEL ABAJAN
PLUMBING-Final 10/31/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved MICHEL ABAJAN
Service/Power Release 10/31/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 10/31/2025 Approved MICHEL ABAJAN
Final 1/30/2026 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 1/30/2026 Approved MICHEL ABAJAN