4433 N KRAFT AVE 91602
Certificate Information: 4433 N KRAFT AVE 91602
- Application / Permit
- 22010-20000-03051
- Plan Check / Job No.
- B22VN09498
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 38' x 57'-8" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | SEAN SHAHMIRI |
| Corrections Issued | 7/28/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 8/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/4/2022 | APPLICANT |
| Applicant returned to address corrections | 10/5/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 11/27/2023 | SEAN SHAHMIRI |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 8/14/2025 | JAVIER RAMOS JR |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2022 | ROMAN GUTIERREZ |
| Permit | Cleared | 8/3/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/11/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 10/1/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 11/22/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 11/22/2022 | ROMAN GUTIERREZ |
| Trees in Parkway | Cleared | 1/24/2023 | ADALBERTO VERA |
| ZI | Cleared | 8/29/2023 | ALEX VELA |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: C35492 | 20140 ZIMMERMAN PLACE SANTA CLARITA, CA 91390 |
| Contractor | B M R Enterprises; Lic. No.: 901546-B | 5250 LANKERSHIM BLVD STE 500 LOS ANGELES, CA 91601 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| DANIEL ORRANTE, (818) 374-1157 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 7/1/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 7/8/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/12/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 7/12/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Underground Mechanical | 7/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/18/2024 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Not Ready for Inspection | ROBERT GOLD |
| Deputy Wood Construction | 8/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/1/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/4/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/4/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/18/2024 | Approved | DAVID MATSON |
| ELECTRICAL-Rough | 11/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/26/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/10/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 12/10/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 12/10/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 12/24/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/10/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 1/24/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/11/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Special/Order Compliance | 3/3/2025 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/6/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Insulation | 3/6/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 3/6/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Order to Comply | 3/7/2025 | OTC Issued | JUAN VALENZUELA |
| Pre-Inspection | 3/11/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/5/2025 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 5/5/2025 | Approved | JUAN VALENZUELA |
| Insulation | 5/5/2025 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/5/2025 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 5/5/2025 | Approved | JUAN VALENZUELA |
| Service/Power Release | 6/16/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 7/18/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 7/30/2025 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 7/30/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 7/30/2025 | Approved | JACK KARGODORIAN |
| Final | 8/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 8/11/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 8/11/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 8/11/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 8/13/2025 | Approved | JAVIER RAMOS JR |
| Final | 8/13/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| PLUMBING-Final | 8/13/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 8/13/2025 | Approved | JAVIER RAMOS JR |