14935 W OTSEGO ST 91403

Certificate Information: 14935 W OTSEGO ST 91403

Application / Permit
22010-20000-03049
Plan Check / Job No.
B22VN09497
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 61'9" X 38' 2-STORY SFD WITH ATTACHED TWO CAR GARAGE AND WITH 20'8" X 7'11" OPEN REAR TRELLIS, NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 RARES BODEA
Corrections Issued 7/5/2022 RARES BODEA
Quality Review Completed 7/14/2022 STEVEN KIM
Building Plans Picked Up 7/14/2022 APPLICANT
Applicant returned to address corrections 8/17/2022 RARES BODEA
Plan Check Approved 8/29/2022 RARES BODEA
Issued 8/29/2022 APPLICANT
CofO in Progress 4/12/2024 THOMAS FINNILA
Permit Finaled 4/13/2024 RUBEN SALAS
CofO Issued 4/13/2024 RUBEN SALAS
Permit Finaled 4/13/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/5/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/5/2022 MEGAN GODINEZ
Sewer availability Cleared 7/5/2022 MEGAN GODINEZ
Low Impact Development Cleared 7/22/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/22/2022 MEGAN GODINEZ
ZI Cleared 7/22/2022 MIGUEL GAMBOA
Hydrant and Access approval Cleared 8/8/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 10/20/2022 Corrections Issued THOMAS FINNILA
Underground Mechanical 10/26/2022 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 11/1/2022 Partial Approval THOMAS FINNILA
Underground Mechanical 11/3/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 11/17/2022 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 11/22/2022 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 12/1/2022 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Conditional Approval JOHN COLEMAN
Deputy Wood Construction 2/6/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 3/3/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 3/10/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 3/10/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 3/13/2023 Partial Approval THOMAS FINNILA
PLUMBING-Rough 3/13/2023 Approved THOMAS FINNILA
ELECTRICAL-Rough 3/21/2023 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/21/2023 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval JOHN COLEMAN
BUILDING-Rough-Frame 4/7/2023 Corrections Issued THOMAS FINNILA
Green Building Rough 4/7/2023 Approved THOMAS FINNILA
HVAC-Rough 4/7/2023 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 4/7/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 4/14/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/18/2023 Partial Approval THOMAS FINNILA
Shower Pan 4/18/2023 Approved THOMAS FINNILA
Insulation 4/26/2023 Approved THOMAS FINNILA
Drywall Nailing 5/1/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/11/2023 Approved THOMAS FINNILA
Underground Mechanical 7/10/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Final 1/3/2024 Approved KEVIN BERBERYAN
Gas Test 1/3/2024 Approved KEVIN BERBERYAN
HVAC-Final 1/3/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Final 1/3/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved KEVIN BERBERYAN
Green Building Final 4/2/2024 Approved THOMAS FINNILA
Final 4/5/2024 OK to Issue CofO THOMAS FINNILA
Service/Power Release 4/5/2024 Approved THOMAS FINNILA
Smoke Detectors 4/5/2024 Approved THOMAS FINNILA