6229 N SYLVIA AVE 91335
Certificate Information: 6229 N SYLVIA AVE 91335
- Application / Permit
- 22010-20000-03034
- Plan Check / Job No.
- B22VN09449
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Current Status
- CofO Issued on 3/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2022 | DANIEL YIP |
| Corrections Issued | 7/9/2022 | DANIEL YIP |
| Applicant returned to address corrections | 8/10/2022 | DANIEL YIP |
| Plan Check Approved | 8/26/2022 | DANIEL YIP |
| Issued | 8/30/2022 | APPLICANT |
| CofO in Progress | 2/26/2024 | JON MCHUGH |
| Permit Finaled | 3/12/2024 | JOHN JANSON |
| CofO Issued | 3/12/2024 | JOHN JANSON |
| Permit Finaled | 3/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/1/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | ROMAN GUTIERREZ |
| ZI | Cleared | 8/25/2022 | DANG NGUYEN |
Contact Information
| Contractor | Remodelme Inc; Lic. No.: 1066731-B | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2023 | Approved | JON MCHUGH |
| Sewer | 9/1/2023 | Not Ready for Inspection | JON MCHUGH |
| Sewer | 9/8/2023 | No Access for Inspection | JUSTIN HAWLEY |
| Sewer | 9/12/2023 | Approved | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 9/15/2023 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 9/15/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 9/20/2023 | Approved | JEFFREY PARD |
| Deputy Wood Construction | 9/28/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 9/29/2023 | Conditional Approval | JON MCHUGH |
| ELECTRICAL-Rough | 10/11/2023 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 10/11/2023 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/11/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/11/2023 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/18/2023 | Partial Approval | JON MCHUGH |
| Shower Pan | 10/18/2023 | Not Ready for Inspection | JON MCHUGH |
| Insulation | 10/25/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/25/2023 | Approved | JON MCHUGH |
| Shower Pan | 10/25/2023 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 10/27/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/3/2023 | Approved | HENRY KIM |
| Final | 1/8/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 1/8/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 1/8/2024 | Approved | JON MCHUGH |
| Final | 2/7/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Not Ready | JON MCHUGH |
| Final | 2/20/2024 | Corrections Issued | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 2/23/2024 | Approved | JON MCHUGH |
| Final | 2/23/2024 | Partial Approval | JON MCHUGH |
| HVAC-Final | 2/23/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 2/23/2024 | Approved | JON MCHUGH |
| Final | 2/26/2024 | OK to Issue CofO | JON MCHUGH |