8850 N MOONBEAM AVE 91402
Certificate Information: 8850 N MOONBEAM AVE 91402
- Application / Permit
- 22010-20000-03014
- Plan Check / Job No.
- B22VN09389
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU AT REAR OF LOT. (E) ADU ON LOT TO BE CONVERTED TO JADU
- Permit Issued
- Issued on 8/31/2022
- Issuing Office
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | JOE VO |
| Corrections Issued | 6/25/2022 | JOE VO |
| Plan Check Approved | 8/26/2022 | JOE VO |
| Issued | 8/31/2022 | APPLICANT |
| CofO in Progress | 3/22/2023 | GREGG CUMMINGS |
| Permit Finaled | 4/5/2023 | DANIEL ORRANTE |
| CofO Issued | 4/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/30/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/6/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 8/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/27/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 9/27/2022 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 10/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/4/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 11/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 12/6/2022 | Approved | GREGG CUMMINGS |
| Sewer | 12/6/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 12/6/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/16/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/16/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 12/16/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/16/2022 | Corrections Issued | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/16/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/21/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/21/2022 | Approved | GREGG CUMMINGS |
| Final | 12/21/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 12/21/2022 | Approved | GREGG CUMMINGS |
| Insulation | 12/21/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/21/2022 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 12/29/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/29/2022 | Partial Approval | GREGG CUMMINGS |
| Pre-Inspection | 2/22/2023 | Approved | GREGG CUMMINGS |
| Final | 3/2/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 3/2/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/2/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 3/2/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/2/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/9/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/14/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 3/14/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 3/14/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 3/14/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 3/14/2023 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 3/14/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 3/14/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/17/2023 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 3/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/21/2023 | Approved | GREGG CUMMINGS |
| Final | 3/21/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 3/21/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 3/21/2023 | Approved | GREGG CUMMINGS |