1707 S STANLEY AVE 90019

Certificate Information: 1707 S STANLEY AVE 90019

Application / Permit
22010-20000-02992
Plan Check / Job No.
B22VN09323
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 20'3" X 18'7" DETACHED 2 CAR GARAGE. ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/23/2022
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 PETER MOSESIAN
Corrections Issued 7/17/2022 PETER MOSESIAN
Quality Review Completed 7/20/2022 OMID HEDAYAT
Building Plans Picked Up 7/25/2022 APPLICANT
Plan Check Approved 11/23/2022 PETER MOSESIAN
Issued 11/23/2022 APPLICANT
CofO in Progress 6/27/2025 WILLIAM MICHALAK
CofO in Progress 6/30/2025 WILLIAM MICHALAK
CofO in Progress 7/2/2025 WILLIAM MICHALAK
Permit Finaled 7/8/2025 CLAUDIO MORENO
CofO Issued 7/8/2025 CLAUDIO MORENO
Permit Finaled 7/8/2025 CLAUDIO MORENO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/10/2022 CINDY QI
Low Impact Development Cleared 8/11/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/22/2022 CINDY QI
Construction near power lines Cleared 11/23/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/25/2023 Corrections Issued GLEN RAND
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 5/7/2025 Partial Approval WILLIAM MICHALAK
Drywall Nailing 5/7/2025 Approved WILLIAM MICHALAK
Final 5/7/2025 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 5/7/2025 Approved WILLIAM MICHALAK
Green Building Final 5/7/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 5/7/2025 Approved WILLIAM MICHALAK
METHANE-Barrier 5/7/2025 Approved WILLIAM MICHALAK
METHANE-Final 5/7/2025 Approved WILLIAM MICHALAK
METHANE-Rough 5/7/2025 Approved WILLIAM MICHALAK
METHANE-Subgrade 5/7/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Not Required WILLIAM MICHALAK
Service/Power Release 5/7/2025 Not Required WILLIAM MICHALAK
Smoke Detectors 5/7/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 6/27/2025 Approved WILLIAM MICHALAK
Final 6/27/2025 OK to Issue CofO WILLIAM MICHALAK
Green Building Final 6/27/2025 Approved WILLIAM MICHALAK