239-241 E 54TH ST 90011

Certificate Information: 239-241 E 54TH ST 90011

Application / Permit
22010-20000-02988
Plan Check / Job No.
B22VN09314
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 2/7/2023
Issuing Office
Current Status
CofO Issued on 11/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 ADRIANA LOPEZ
Corrections Issued 7/17/2022 ADRIANA LOPEZ
Quality Review Completed 7/18/2022 GARO TELMI
Plan Check Approved 12/27/2022 ADRIANA LOPEZ
Issued 2/7/2023 APPLICANT
CofO in Progress 10/28/2023 ALEJANDRO DE ARTOLA
CofO Issued 11/3/2023 DEROLD HAUFF
Permit Finaled 11/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 7/28/2022 NATHAN ROMINE
Address approval Cleared 8/11/2022 JEANETTE VONG
Sewer availability Cleared 8/17/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/18/2022 JEANETTE VONG
Low Impact Development Cleared 8/29/2022 SARAH YOUSSEF
Hydrant and Access approval Cleared 9/3/2022 RUEL COLE
Roof/Waste drainage to street Cleared 9/3/2022 JEANETTE VONG
Highway dedication Cleared 9/26/2022 TREVOR QUAN
SB8 RUD Cleared 10/24/2022 DORIS KWOK

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 5/24/2023 Partial Approval STUART CHAPMAN
Wood Frame 5/24/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval STUART CHAPMAN
Insulation 5/25/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Approved BRENDAN MORELLI
HVAC-Rough 6/28/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 6/28/2023 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 6/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/29/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 6/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 6/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 6/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 6/30/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/3/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 7/3/2023 Approved ALEJANDRO DE ARTOLA
Insulation 7/3/2023 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/19/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 7/19/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 9/11/2023 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/26/2023 Approved ALEJANDRO DE ARTOLA
Green Building Final 10/26/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/26/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/26/2023 Approved ALEJANDRO DE ARTOLA
Final 10/27/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/27/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/27/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/27/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 10/27/2023 Approved ALEJANDRO DE ARTOLA