152-154 W 42ND PL 90037
Certificate Information: 152-154 W 42ND PL 90037
- Application / Permit
- 22010-20000-02987
- Plan Check / Job No.
- B22VN09313
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Current Status
- CofO Issued on 6/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | CARLOS MONTES |
| Corrections Issued | 7/3/2022 | CARLOS MONTES |
| Quality Review Completed | 7/20/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/14/2022 | CARLOS MONTES |
| Plan Check Approved | 10/18/2022 | CARLOS MONTES |
| Issued | 12/20/2022 | APPLICANT |
| CofO in Progress | 6/7/2023 | BRENDAN MORELLI |
| CofO Issued | 6/25/2023 | DEROLD HAUFF |
| Permit Finaled | 6/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/19/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/11/2022 | JEANETTE VONG |
| Address approval | Cleared | 8/16/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 8/16/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 9/3/2022 | RUEL COLE |
| Permit | Cleared | 11/21/2022 | STEVE MELGAR |
| Trees in Parkway | Cleared | 12/8/2022 | ADALBERTO VERA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 1/24/2023 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/30/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/30/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 1/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 2/1/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 2/21/2023 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 3/16/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/16/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/17/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 3/17/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/17/2023 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/17/2023 | Approved | STUART CHAPMAN |
| Insulation | 3/21/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/28/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 3/28/2023 | Partial Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/12/2023 | Approved | BRENDAN MORELLI |
| Service/Power Release | 4/12/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/5/2023 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/24/2023 | Approved | STUART CHAPMAN |
| Final | 5/24/2023 | Corrections Issued | STUART CHAPMAN |
| Gas Test | 5/24/2023 | Approved | STUART CHAPMAN |
| Green Building Final | 5/24/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 5/24/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 5/24/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 5/24/2023 | Approved | STUART CHAPMAN |
| Smoke Detectors | 5/24/2023 | Approved | STUART CHAPMAN |
| Final | 6/6/2023 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 6/6/2023 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 6/20/2023 | Partial Inspection | BRENDAN MORELLI |