17515 W GILMORE ST 91406
Certificate Information: 17515 W GILMORE ST 91406
- Application / Permit
- 22010-20000-02983
- Plan Check / Job No.
- B22VN09309
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New detached accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Current Status
- CofO Issued on 6/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | MONICA RAMIREZ |
| Corrections Issued | 7/26/2022 | MONICA RAMIREZ |
| Quality Review Completed | 8/3/2022 | RODOLFO ARIAS |
| Plan Check Approved | 11/10/2022 | MONICA RAMIREZ |
| Issued | 11/10/2022 | APPLICANT |
| CofO in Progress | 5/25/2023 | JON MCHUGH |
| CofO in Progress | 5/25/2023 | JON MCHUGH |
| CofO in Progress | 6/2/2023 | JON MCHUGH |
| Permit Finaled | 6/2/2023 | JOHN JANSON |
| CofO Issued | 6/2/2023 | JOHN JANSON |
| Permit Finaled | 6/2/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/8/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 9/29/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/26/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Gopro Remodeling Inc; Lic. No.: 989654-B | , |
| Engineer | Kaballo,, Amir; Lic. No.: C90707 | 152 S SWALL DR BEVERLY HILLS, CA 90211 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/17/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 11/17/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 11/21/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Approved | JON MCHUGH |
| Gas Test | 12/9/2022 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 12/9/2022 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 12/12/2022 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 12/12/2022 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 12/14/2022 | Approved | JON MCHUGH |
| HVAC-Rough | 12/14/2022 | Corrections Issued | JON MCHUGH |
| Wood Frame | 12/14/2022 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 12/19/2022 | Approved | JON MCHUGH |
| Insulation | 12/21/2022 | Not Ready for Inspection | JON MCHUGH |
| Insulation | 12/22/2022 | Approved | JON MCHUGH |
| Drywall Nailing | 12/28/2022 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 12/28/2022 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | JON MCHUGH |
| Final | 4/27/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/27/2023 | Approved | JON MCHUGH |
| Green Building Rough | 4/27/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 4/27/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 4/27/2023 | Corrections Issued | JON MCHUGH |
| Verify Sprinkler Sign Off | 4/27/2023 | Approved | JON MCHUGH |
| Final | 5/9/2023 | Not Ready for Inspection | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Gas Company | SEAN WIRCH |
| Service/Power Release | 5/9/2023 | Approved | SEAN WIRCH |
| Smoke Detectors | 5/9/2023 | Approved | SEAN WIRCH |
| Final | 5/26/2023 | OK to Issue CofO | JON MCHUGH |