4528 N MATILIJA AVE 91423

Certificate Information: 4528 N MATILIJA AVE 91423

Application / Permit
22010-20000-02977
Plan Check / Job No.
B22VN09294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 48'-6" x 99'-9" IRR. SHAPED 2-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND OPEN TRELLIS; NFPA-13D THRU-OUT
Permit Issued
Issued on 7/8/2024
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 SEAN SHAHMIRI
Corrections Issued 6/28/2022 SEAN SHAHMIRI
Quality Review Completed 6/30/2022 OMID HEDAYAT
Building Plans Picked Up 12/15/2022 APPLICANT
Applicant returned to address corrections 4/24/2023 SEAN SHAHMIRI
Applicant returned to address corrections 5/2/2023 SEAN SHAHMIRI
Plan Check Approved 5/16/2023 SEAN SHAHMIRI
Issued 7/8/2024 APPLICANT
CofO in Progress 1/20/2026 MISAEL ESPARZA
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/17/2022 RUEL COLE
Address approval Cleared 7/25/2022 CARLOS AGUILERA
Permit Cleared 7/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/26/2022 CARLOS AGUILERA
Sewer availability Cleared 7/26/2022 CARLOS AGUILERA
ZA Case Cleared 11/21/2022 NATHAN ROMINE
ZA Case Cleared 11/21/2022 NATHAN ROMINE
ZI Cleared 11/21/2022 NATHAN ROMINE
Low Impact Development Cleared 2/22/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 2/22/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/14/2024 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 8/27/2024 Partial Approval VINCENT HANLEY
Sewer 8/27/2024 Approved VINCENT HANLEY
Underground Mechanical 8/27/2024 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/13/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/13/2024 Partial Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/4/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 12/20/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Corrections Issued MISAEL ESPARZA
Gas Test 2/20/2025 Partial Approval MISAEL ESPARZA
HVAC-Rough 2/20/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 2/20/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/25/2025 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Rough 2/25/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved MISAEL ESPARZA
Green Building Rough 2/25/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 2/25/2025 Corrections Issued MISAEL ESPARZA
MERV13>=Rough 2/25/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 2/25/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/27/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 2/27/2025 Approved MISAEL ESPARZA
Green Building Rough 2/27/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 2/27/2025 Approved MISAEL ESPARZA
Insulation 3/7/2025 Approved MICHAEL CORTEZ
Shower Pan 3/12/2025 Approved MISAEL ESPARZA
Drywall Nailing 3/14/2025 Approved MISAEL ESPARZA
Green Building Rough 3/14/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/17/2025 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 3/21/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/25/2025 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 8/25/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 9/2/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 9/10/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 9/23/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 9/25/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 9/25/2025 No Access for Inspection MISAEL ESPARZA
PLUMBING-Final 9/25/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/16/2025 Approved MISAEL ESPARZA
HVAC-Final 10/16/2025 Approved MISAEL ESPARZA
Final 11/17/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 11/17/2025 Approved MISAEL ESPARZA
MERV13>=Final 11/17/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved MISAEL ESPARZA
Service/Power Release 11/17/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/17/2025 Approved MISAEL ESPARZA
Final 1/15/2026 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 1/15/2026 Approved MISAEL ESPARZA