13606 W BASSETT ST 91405

Certificate Information: 13606 W BASSETT ST 91405

Application / Permit
22010-20000-02971
Plan Check / Job No.
B22VN09267
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 37'-0" X 29'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 10/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 ARTIN ZARUKIAN
Corrections Issued 6/18/2022 ARTIN ZARUKIAN
Plan Check Approved 9/22/2022 JEROME MAGAT PALMA
Issued 10/12/2022 APPLICANT
CofO in Progress 10/25/2023 KIRK SANDERS
Permit Finaled 11/30/2023 RUBEN SALAS
CofO Issued 11/30/2023 RUBEN SALAS
Permit Finaled 11/30/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/25/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/30/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/30/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 7/22/2022 KURT CORRAL
Construction near power lines Cleared 9/4/2022 RIDWAN HARDY
Low Impact Development Cleared 9/19/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 9/21/2022 DAGOVERTO GUERRERO

Contact Information

Contractor L A Construction Group Inc; Lic. No.: 873259-B 18607 VENTURA BLVD #205      TARZANA, CA 91356

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/16/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Approved KIRK SANDERS
HVAC-Rough 5/23/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 6/12/2023 Approved JOHN COLEMAN
Green Building Rough 6/12/2023 Approved JOHN COLEMAN
HVAC-Rough 6/12/2023 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 6/12/2023 Approved JOHN COLEMAN
Insulation 6/15/2023 Approved KIRK SANDERS
Drywall Nailing 6/20/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/20/2023 Approved JUAN VALENZUELA
Shower Pan 6/20/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 9/28/2023 Corrections Issued KIRK SANDERS
Final 9/28/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 9/28/2023 Approved KIRK SANDERS
Green Building Final 9/28/2023 Approved KIRK SANDERS
HVAC-Final 9/28/2023 Approved KIRK SANDERS
PLUMBING-Final 9/28/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 9/28/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 9/28/2023 Approved KIRK SANDERS
ELECTRICAL-Final 10/16/2023 Not Ready for Inspection KIRK SANDERS
Final 10/16/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Final 10/16/2023 Approved KIRK SANDERS
PLUMBING-Final 10/16/2023 Approved KIRK SANDERS
Service/Power Release 10/16/2023 Not Ready for Inspection KIRK SANDERS
Final 10/20/2023 Corrections Issued KIRK SANDERS
Final 10/24/2023 OK to Issue CofO KIRK SANDERS
Service/Power Release 10/24/2023 Approved KIRK SANDERS