24264 W HIGHLANDER ROAD 91307
Certificate Information: 24264 W HIGHLANDER ROAD 91307
- Application / Permit
- 22010-20000-02968
- Plan Check / Job No.
- B22VN09253
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Current Status
- CofO Issued on 2/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | KEVIN MORALES |
| Corrections Issued | 7/5/2022 | KEVIN MORALES |
| Quality Review Completed | 7/5/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/4/2022 | KEVIN MORALES |
| Plan Check Approved | 8/11/2022 | KEVIN MORALES |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 12/14/2022 | KRISTEN BEVERIDGE |
| Permit Finaled | 2/21/2023 | JOHN JANSON |
| CofO Issued | 2/21/2023 | JOHN JANSON |
| Permit Finaled | 2/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/15/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/15/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/25/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Underground Mechanical | 8/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/31/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 8/31/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Reinf. Concrete | 9/1/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/23/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/23/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/23/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Shower Pan | 9/23/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 9/30/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/30/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/30/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Shower Pan | 9/30/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/7/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/7/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/7/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/7/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/7/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 10/7/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/11/2022 | Partial Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/17/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 11/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 11/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 11/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 11/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 11/8/2022 | Partial Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 11/22/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 11/22/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/22/2022 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 11/22/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 12/5/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| Service/Power Release | 12/5/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Final | 12/13/2022 | Approved | KRISTEN CAUSEY |
| Final | 12/13/2022 | OK to Issue CofO | KRISTEN CAUSEY |
| HVAC-Final | 12/13/2022 | Approved | KRISTEN CAUSEY |
| PLUMBING-Final | 12/13/2022 | Approved | KRISTEN CAUSEY |
| Service/Power Release | 12/13/2022 | Approved | KRISTEN CAUSEY |