5842 N SATSUMA AVE 91601

Certificate Information: 5842 N SATSUMA AVE 91601

Application / Permit
22010-20000-02967
Plan Check / Job No.
B22VN09251
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW DETACHED ADU PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 10/10/2024
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2022 APPLICANT
Assigned to Plan Check Engineer 6/29/2022 KHUONG TRUONG
Corrections Issued 6/30/2022 KHUONG TRUONG
Applicant returned to address corrections 8/5/2022 KHUONG TRUONG
Plan Check Approved 11/17/2022 KHUONG TRUONG
Issued 10/10/2024 APPLICANT
CofO in Progress 3/28/2025 JOSE AVILA
Permit Finaled 5/2/2025 RUBEN SALAS
CofO Issued 5/2/2025 RUBEN SALAS
Permit Finaled 5/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/20/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/12/2022 MEGAN GODINEZ
Sewer availability Cleared 9/12/2022 MEGAN GODINEZ
Construction near power lines Cleared 9/30/2022 RIDWAN HARDY
Low Impact Development Cleared 11/9/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 11/16/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/15/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/18/2024 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/22/2024 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/25/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 11/20/2024 Approved JOSE AVILA
ELECTRICAL-Rough 11/20/2024 Approved JOSE AVILA
Green Building Rough 11/20/2024 Approved JOSE AVILA
HVAC-Rough 11/20/2024 Approved JOSE AVILA
PLUMBING-Rough 11/20/2024 Approved JOSE AVILA
Sewer 11/20/2024 Approved JOSE AVILA
Verify Sprinkler Sign Off 11/20/2024 Approved JOSE AVILA
Insulation 11/27/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/27/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 12/10/2024 Approved JOSE AVILA
PLUMBING-Final 2/24/2025 Approved JOSE AVILA
ELECTRICAL-Final 3/14/2025 Approved JOSE AVILA
Service/Power Release 3/14/2025 Approved JOSE AVILA
Service/Power Release 3/27/2025 Approved JOSE AVILA
Final 3/28/2025 OK to Issue CofO JOSE AVILA
Footing/Foundation/Slab 3/28/2025 Approved JOSE AVILA
Green Building Final 3/28/2025 Approved JOSE AVILA
Smoke Detectors 3/28/2025 Approved JOSE AVILA