354 1/4-356 1/4 W 45TH ST 90037
Certificate Information: 354 1/4-356 1/4 W 45TH ST 90037
- Application / Permit
- 22010-20000-02963
- Plan Check / Job No.
- B22VN09247
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Two new detached 457sf ADUs.
- Permit Issued
- Issued on 6/28/2023
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 7/28/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/28/2022 | GARO TELMI |
| Plan Check Approved | 6/27/2023 | ARSALAN SHABESTARI |
| Issued | 6/28/2023 | APPLICANT |
| CofO in Progress | 10/11/2024 | ALEJANDRO DE ARTOLA |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | JEANIE LAM |
| Highway dedication | Cleared | 8/3/2022 | JEANIE LAM |
| Sewer availability | Cleared | 8/3/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 10/5/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/6/2022 | JEANIE LAM |
Contact Information
| Contractor | Mr Build Home Improvement Company; Lic. No.: 439166-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/20/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 9/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/25/2023 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 12/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 2/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 2/14/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/12/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/20/2024 | Approved | CRAIG DAVIS |
| Shower Pan | 3/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/28/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 3/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 4/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/5/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 4/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/10/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |