Pre-Inspection
|
3/1/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
3/27/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/27/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
3/28/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/5/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/8/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/10/2024
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
4/10/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/11/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/17/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
4/17/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
4/17/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/19/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
4/19/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
4/30/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
5/22/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/23/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/7/2024
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
6/7/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/7/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
6/7/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
6/20/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/21/2024
|
Approved
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
6/26/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
6/27/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/5/2024
|
Conditional Approval
|
ANDREW DORSO
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/30/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
8/30/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Structural Steel Frame
|
8/30/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
8/30/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
10/7/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Structural Steel Frame
|
10/7/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
10/7/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
10/7/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/9/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
10/9/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Structural Steel Frame
|
10/9/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
11/13/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
11/18/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
11/19/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
11/19/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
11/19/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
12/23/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
12/23/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
12/23/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
12/24/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
2/4/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Structural Steel Frame
|
2/4/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
2/4/2025
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
2/4/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Structural Steel Frame
|
2/6/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
2/6/2025
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
2/6/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
2/7/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Insulation
|
2/12/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
2/12/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
2/19/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/21/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
2/24/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/7/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Final
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Final
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
SGSOV-Seismic Gas S/O Valve
|
5/28/2025
|
SGSOV Not Ready
|
JOHN KITCKO
|
|
Smoke Detectors
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Structural Steel Frame
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/28/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Final
|
8/25/2025
|
Corrections Issued
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
8/25/2025
|
Approved
|
ROBERT DAVIS
|
|
Green Building Final
|
8/25/2025
|
Approved
|
ROBERT DAVIS
|
|
Reinforced Masonry Frame
|
8/25/2025
|
Approved
|
ROBERT DAVIS
|
|
SGSOV-Seismic Gas S/O Valve
|
8/25/2025
|
SGSOV No Gas
|
ROBERT DAVIS
|
|
Smoke Detectors
|
8/25/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Structural Steel Frame
|
8/25/2025
|
Approved
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
8/25/2025
|
Approved
|
ROBERT DAVIS
|
|
Wood Frame
|
8/25/2025
|
Approved
|
ROBERT DAVIS
|
|
Final
|
9/23/2025
|
OK to Issue CofO
|
GREGORY POMISH
|
|
Smoke Detectors
|
9/23/2025
|
Approved
|
GREGORY POMISH
|