194 S GREENFIELD AVE 90049

Certificate Information: 194 S GREENFIELD AVE 90049

Application / Permit
22010-20000-02923
Plan Check / Job No.
B22VN09138
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 41'-6" X 18' (TWO) STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 3/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/27/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/30/2022 OMID HEDAYAT
Building Plans Picked Up 7/6/2022 APPLICANT
Applicant returned to address corrections 2/15/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 3/3/2023 SEWADA ZADOORAN MILAGARDI
Issued 3/21/2023 APPLICANT
CofO in Progress 9/10/2024 CARLOS MATAMOROS
Permit Finaled 9/10/2024 RICHARD STEINBACH
CofO Issued 9/10/2024 RICHARD STEINBACH
Permit Finaled 9/10/2024 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 11/17/2022 PEDRO AYALA
Low Impact Development Cleared 12/20/2022 ANTHONY VARGAS
Address approval Cleared 12/28/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 12/28/2022 CATHERINE ADROVER
Sewer availability Cleared 12/28/2022 CATHERINE ADROVER
Hydrant and Access approval Cleared 1/17/2023 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 2/2/2023 ANTHONY MAINEZ
Watercourse Cleared 2/2/2023 ANTHONY MAINEZ
GPI Written Notices Cleared 2/15/2023 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 2/15/2023 SEWADA ZADOORAN MILAGARDI

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Pristine Construction Inc; Lic. No.: 939885-B 14320 VENTURA BL   #320    SHERMAN OAKS, CA 91423

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/30/2023 Partial Approval CARLOS MATAMOROS
Sewer 5/30/2023 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 6/14/2023 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 6/15/2023 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval CARLOS MATAMOROS
HVAC-Rough 10/3/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 10/3/2023 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 10/5/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/5/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 10/5/2023 Approved CHRISTOPHER WILSON
HVAC-Rough 10/11/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 10/13/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/16/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 10/19/2023 Approved CARLOS MATAMOROS
Structural Steel Frame 10/19/2023 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 10/23/2023 Approved CARLOS MATAMOROS
FLOOD-Proofing Certificate 10/23/2023 Approved CARLOS MATAMOROS
Green Building Rough 10/23/2023 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/23/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/26/2023 Partial Approval STEPHANIE SWANSON
Shower Pan 11/16/2023 Approved CHRISTOPHER WILSON
Insulation 11/30/2023 Corrections Issued CHRISTOPHER WILSON
Insulation 12/1/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 12/1/2023 Approved STEPHANIE SWANSON
Drywall Nailing 1/10/2024 Approved MICHAEL PELHAM
Gas Test 1/10/2024 Approved MICHAEL PELHAM
PLUMBING-Final 6/5/2024 Approved SEAN HAUPT
ELECTRICAL-Final 6/20/2024 Approved CARLOS MATAMOROS
HVAC-Final 6/20/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 6/25/2024 Approved CARLOS MATAMOROS
HVAC-Final 6/25/2024 Approved CARLOS MATAMOROS
Service/Power Release 9/9/2024 Approved CARLOS MATAMOROS
Final 9/10/2024 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 9/10/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/10/2024 Approved CARLOS MATAMOROS