3004 S SHRINE PL 90007

Certificate Information: 3004 S SHRINE PL 90007

Application / Permit
22010-20000-02918
Plan Check / Job No.
B22VN09132
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c)(d)
Permit Issued
Issued on 11/18/2022
Issuing Office
Current Status
CofO Issued on 11/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 NILOOFAR MEHRAIN
Corrections Issued 6/28/2022 TROY DEGUZMAN
Quality Review Completed 7/7/2022 OMID HEDAYAT
Applicant returned to address corrections 10/20/2022 NILOOFAR MEHRAIN
Plan Check Approved 11/8/2022 NILOOFAR MEHRAIN
No Progress 11/16/2022 NILOOFAR MEHRAIN
Plan Check Approved 11/16/2022 NILOOFAR MEHRAIN
Issued 11/18/2022 APPLICANT
CofO in Progress 10/27/2023 ALEJANDRO DE ARTOLA
CofO Issued 11/3/2023 DEROLD HAUFF
Permit Finaled 11/3/2023 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 7/1/2022 JASON CHAN
Address approval Cleared 7/14/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/14/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 7/14/2022 JEANETTE VONG
Sewer availability Cleared 7/14/2022 JEANETTE VONG
Redevelopment Project Area Cleared 7/25/2022 DAVID URITA
ZI Cleared 7/25/2022 DAVID URITA
Hydrant and Access approval Cleared 8/1/2022 MATTHEW CRAIG
Green Code Cleared 10/21/2022 TROY DEGUZMAN

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 4043 IRVING PL SUITE B      CULVER CITY, CA 90232
Contractor Owner-Builder       ,
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/9/2023 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 2/9/2023 Not Ready for Inspection BRENDAN MORELLI
METHANE-Barrier 2/9/2023 Approved BRENDAN MORELLI
METHANE-Subgrade 2/9/2023 Approved BRENDAN MORELLI
Pre-Inspection 2/9/2023 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 2/13/2023 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 2/22/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 3/13/2023 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 3/13/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Partial Approval STUART CHAPMAN
Insulation 3/17/2023 Approved STUART CHAPMAN
Deputy Wood Construction 4/4/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Partial Approval BRENDAN MORELLI
Green Building Rough 4/5/2023 Not Ready for Inspection BRENDAN MORELLI
METHANE-Rough 4/5/2023 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 4/5/2023 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 6/5/2023 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 6/9/2023 Approved BRENDAN MORELLI
HVAC-Rough 6/9/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 6/9/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 6/21/2023 Approved BRENDAN MORELLI
Green Building Rough 6/21/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 6/21/2023 Approved BRENDAN MORELLI
Insulation 6/28/2023 Approved BRENDAN MORELLI
Drywall Nailing 7/6/2023 Approved BRENDAN MORELLI
Green Building Rough 7/6/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 7/6/2023 Approved BRENDAN MORELLI
Final 8/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 8/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 8/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 9/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/10/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 10/10/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 10/10/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/16/2023 Approved ALEJANDRO DE ARTOLA
Green Building Final 10/16/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/16/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/26/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 10/26/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/26/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/26/2023 Approved ALEJANDRO DE ARTOLA