5653 N SATSUMA AVE 91601

Certificate Information: 5653 N SATSUMA AVE 91601

Application / Permit
22010-20000-02917
Plan Check / Job No.
B22VN09131
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan (1) NEW 2 STORY DUPLEX
Permit Issued
Issued on 3/29/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 JAD BASMA
Corrections Issued 7/20/2022 JAD BASMA
Quality Review Completed 7/29/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/7/2022 JAD BASMA
Applicant returned to address corrections 11/23/2022 JAD BASMA
Plan Check Approved 12/8/2022 JAD BASMA
Plan Check Approved 3/7/2023 JAD BASMA
Issued 3/29/2023 APPLICANT
CofO in Progress 7/8/2024 JOSE AVILA
No Progress 7/10/2024 JOSE AVILA
CofO in Progress 7/10/2024 JOSE AVILA
Permit Finaled 7/17/2024 RUBEN SALAS
CofO Issued 7/17/2024 RUBEN SALAS
Permit Finaled 7/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/19/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/20/2022 ROMAN GUTIERREZ
Sewer availability Cleared 7/20/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 8/5/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/9/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 9/3/2022 RUEL COLE
Frnt yard landscape/Water mgmt Cleared 10/21/2022 RUBEN VASQUEZ

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/18/2023 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/24/2023 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 9/21/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 9/21/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/22/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/22/2023 Approved JOHN HAYES
Verify Sprinkler Sign Off 9/22/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/29/2023 Approved JOHN HAYES
Interior/Exterior Lathing 9/29/2023 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 9/29/2023 Approved JOHN HAYES
Insulation 10/11/2023 Corrections Issued JOHN HAYES
Shower Pan 10/11/2023 Approved JOHN HAYES
Special/Order Compliance 10/12/2023 Approved JOHN HAYES
Drywall Nailing 10/20/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 10/20/2023 Approved ROBERT GOLD
Underground Mechanical 1/29/2024 Approved JOHN HAYES
Underground Mechanical 2/1/2024 Approved JOHN HAYES
Gas Test 5/13/2024 Approved JOSE AVILA
PLUMBING-Final 5/13/2024 Approved JOSE AVILA
ELECTRICAL-Final 5/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 5/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 5/16/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 6/3/2024 Corrections Issued JOSE AVILA
Service/Power Release 6/3/2024 Not Ready for Inspection JOSE AVILA
Service/Power Release 6/18/2024 Approved JOSE AVILA
Final 7/8/2024 OK to Issue CofO JOSE AVILA
Special/Order Compliance 7/10/2024 Corrections Issued JOSE AVILA