7412 S BUDLONG AVE 90044

Certificate Information: 7412 S BUDLONG AVE 90044

Application / Permit
22010-20000-02900
Plan Check / Job No.
B22VN09103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ATTACH (N) 21'-4" X 32'-3" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED PATIO COVER TO (E) 18' X 12' GARAGE ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/27/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 6/29/2022 OMID HEDAYAT
Building Plans Picked Up 7/11/2022 APPLICANT
Applicant returned to address corrections 11/23/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 12/20/2022 SEWADA ZADOORAN MILAGARDI
Issued 1/13/2023 APPLICANT
CofO in Progress 3/26/2024 MICHAEL LEWIS
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/23/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/1/2022 STEVE MELGAR
Sewer availability Cleared 8/1/2022 STEVE MELGAR
Hydrant and Access approval Cleared 9/18/2022 JOHN CONNEALLY
Construction near power lines Cleared 9/28/2022 RIDWAN HARDY
Construction within easement Cleared 9/28/2022 RIDWAN HARDY
Low Impact Development Cleared 10/26/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/28/2022 ABEL CASILLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 4/24/2023 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 4/25/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 5/11/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 6/28/2023 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 9/21/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Approved MICHAEL LEWIS
HVAC-Rough 9/21/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 9/21/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/28/2023 Approved MICHAEL LEWIS
Green Building Rough 9/28/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 9/28/2023 Approved MICHAEL LEWIS
Insulation 10/4/2023 Not Ready for Inspection MICHAEL LEWIS
Insulation 10/5/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/11/2023 Approved MICHAEL LEWIS
Underground Mechanical 10/11/2023 Not Ready for Inspection MICHAEL LEWIS
Interior/Exterior Lathing 10/16/2023 Not Ready for Inspection RONNIE MINDANAO
Shower Pan 10/16/2023 Not Ready for Inspection RONNIE MINDANAO
Underground Mechanical 10/16/2023 Not Ready for Inspection RONNIE MINDANAO
Interior/Exterior Lathing 10/17/2023 Not Ready for Inspection STUART CHAPMAN
Shower Pan 10/17/2023 Approved STUART CHAPMAN
Underground Mechanical 10/17/2023 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 10/20/2023 Approved MICHAEL LEWIS
Sewer 10/24/2023 Approved MICHAEL LEWIS
Underground Mechanical 10/24/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Not Ready MICHAEL LEWIS
Final 12/28/2023 Corrections Issued MICHAEL LEWIS
Green Building Final 12/28/2023 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 12/28/2023 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/11/2024 SGSOV Approved MICHAEL LEWIS
Final 1/16/2024 Partial Inspection MICHAEL LEWIS
Green Building Final 1/16/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 1/16/2024 Corrections Issued MICHAEL LEWIS
Final 1/23/2024 Corrections Issued MICHAEL LEWIS
Smoke Detectors 1/23/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 1/25/2024 Partial Approval MICHAEL LEWIS
Service/Power Release 1/25/2024 Approved MICHAEL LEWIS
Final 2/27/2024 Corrections Issued MICHAEL LEWIS
Service/Power Release 2/27/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 3/20/2024 Approved MICHAEL LEWIS
Final 3/20/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 3/20/2024 Approved MICHAEL LEWIS