11668 W MARGATE ST 91601
Certificate Information: 11668 W MARGATE ST 91601
- Application / Permit
- 22010-20000-02897
- Plan Check / Job No.
- B22VN09079
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan (E) GARAGE TO BE CONVERTED TO NEW ACCESSORY DWELLING UNIT PER ORDINANCE. FIRE SPRINKLER NFPA 13D THROUGHOUT.
- Permit Issued
- Issued on 10/13/2022
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/27/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 9/13/2022 | FARSHAD ALIMOHAMADI |
| Issued | 10/13/2022 | APPLICANT |
| CofO in Progress | 12/13/2023 | JOHN COLEMAN |
| CofO in Progress | 1/16/2024 | JOHN COLEMAN |
| CofO in Progress | 1/16/2024 | JOHN COLEMAN |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 6/28/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 8/16/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
| Specific Plan | Cleared | 8/23/2022 | ERIN NASH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/23/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/25/2023 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 3/20/2023 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 3/20/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 3/24/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 4/25/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 4/25/2023 | Approved | JACK KARGODORIAN |
| Insulation | 5/3/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 5/3/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 5/3/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 5/9/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/16/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/6/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 9/6/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/6/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | JOHN COLEMAN |
| Final | 12/13/2023 | OK to Issue CofO | JOHN COLEMAN |
| MERV13>=Final | 12/13/2023 | Approved | JOHN COLEMAN |
| MERV13>=Rough | 12/13/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 12/13/2023 | Approved | JOHN COLEMAN |
| Service/Power Release | 1/16/2024 | Approved | JOHN COLEMAN |