7807 N OAKDALE AVE 91306

Certificate Information: 7807 N OAKDALE AVE 91306

Application / Permit
22010-20000-02892
Plan Check / Job No.
B22VN09075
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ONE-STORY DETACHED ADU
Permit Issued
Issued on 3/8/2023
Issuing Office
Current Status
CofO Issued on 11/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 JOE VO
Corrections Issued 6/17/2022 JOE VO
Plan Check Approved 2/25/2023 JOE VO
Issued 3/8/2023 APPLICANT
CofO in Progress 11/14/2023 ALEXANDER HANDY
Permit Finaled 11/16/2023 JOHN JANSON
CofO Issued 11/16/2023 JOHN JANSON
Permit Finaled 11/16/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/22/2022 JOSE DUARTE-DIAZ
ZA Case Cleared 7/26/2022 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 9/19/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 9/19/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 2/17/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 2/22/2023 MEGAN GODINEZ

Contact Information

Contractor Kotov Construction Inc; Lic. No.: 1062227-B       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/30/2023 Corrections Issued JON MCHUGH
Pre-Inspection 4/5/2023 Conditional Approval JEFFREY BULL
Underground Mechanical 4/18/2023 Approved ALEXANDER HANDY
Footing/Foundation/Slab 4/24/2023 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval SEAN WIRCH
Rough-Elec/Plmb/HVAC 5/24/2023 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 5/30/2023 Approved ALEXANDER HANDY
ELECTRICAL-Rough 5/30/2023 Approved ALEXANDER HANDY
Green Building Rough 5/30/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 5/30/2023 Partial Approval ALEXANDER HANDY
Verify Sprinkler Sign Off 5/30/2023 Approved ALEXANDER HANDY
Insulation 6/2/2023 Conditional Approval ALEXANDER HANDY
Drywall Nailing 6/8/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 6/21/2023 Approved ALEXANDER HANDY
Sewer 7/28/2023 Approved ALEXANDER HANDY
Underground Mechanical 7/28/2023 Approved ALEXANDER HANDY
Final 9/19/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 9/19/2023 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved ALEXANDER HANDY
Service/Power Release 9/19/2023 Not Required ALEXANDER HANDY
Smoke Detectors 9/19/2023 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Final 11/13/2023 Approved ALEXANDER HANDY
Final 11/13/2023 OK to Issue CofO ALEXANDER HANDY
Green Building Final 11/13/2023 Approved ALEXANDER HANDY
HVAC-Final 11/13/2023 Approved ALEXANDER HANDY
PLUMBING-Final 11/13/2023 Approved ALEXANDER HANDY
Smoke Detectors 11/13/2023 Approved ALEXANDER HANDY