10148 N MCVINE AVE 91040
Certificate Information: 10148 N MCVINE AVE 91040
- Application / Permit
- 22010-20000-02854
- Plan Check / Job No.
- B22VN08912
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPlan :New 2-story structure which combines an Accessory Dwelling Unit (at 2nd level) with Accessory Living Quarters and storage/workshop (at 1st level). Attached covered patio at 1st level . ADU is per LAMC 12.22A.33(c)-(d) . Roof deck provided with required guard rails No kitchen allowed for Accessory Living Quarter and cannot be rented and cannot be used as a separate dwelling unit.
- Permit Issued
- Issued on 11/23/2022
- Issuing Office
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2022 | HANS SANTIAGO |
| Corrections Issued | 6/16/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 7/19/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/2/2022 | HANS SANTIAGO |
| Plan Check Approved | 11/17/2022 | ANDREW SANTIAGO |
| No Progress | 11/17/2022 | ANDREW SANTIAGO |
| Issued | 11/23/2022 | APPLICANT |
| CofO in Progress | 7/12/2025 | DAVID ANDERSON |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
| CofO Issued | 8/19/2025 | RUBEN SALAS |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 7/22/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 9/7/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 9/12/2022 | KURT CORRAL |
| GPI Written Notices | Cleared | 11/2/2022 | ANDREW SANTIAGO |
| Grading Pre-Inspection | Cleared | 11/2/2022 | ANDREW SANTIAGO |
| Roof/Waste drainage to street | Cleared | 11/17/2022 | ROMAN GUTIERREZ |
| Public Works-Highway Ded. | Cleared | 11/17/2022 | ROMAN GUTIERREZ |
| Public Works-Open Permits | Cleared | 11/17/2022 | ROMAN GUTIERREZ |
| Public Works-Sewers | Cleared | 11/17/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/21/2023 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 4/21/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 4/21/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 4/21/2023 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/25/2023 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 12/29/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/29/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 12/29/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/27/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Partial Approval | DAVID ANDERSON |
| Light Gage Steel Frame | 3/27/2024 | Corrections Issued | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 3/27/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Partial Approval | DAVID ANDERSON |
| Light Gage Steel Frame | 4/25/2024 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/5/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 7/5/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/23/2024 | Partial Approval | DAVID ANDERSON |
| Wood Frame | 7/23/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/1/2024 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 11/1/2024 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/4/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/4/2024 | Approved | DAVID ANDERSON |
| Insulation | 12/6/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/13/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 1/21/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/27/2025 | Approved | DAVID ANDERSON |
| Final | 6/30/2025 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 6/30/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 6/30/2025 | Approved | DAVID ANDERSON |
| Structural Steel Frame | 6/30/2025 | Approved | DAVID ANDERSON |
| Final | 7/8/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 7/8/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 7/11/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 7/11/2025 | Approved | DAVID ANDERSON |
| Service/Power Release | 7/11/2025 | Approved | DAVID ANDERSON |