13944 W WYANDOTTE ST 91405

Certificate Information: 13944 W WYANDOTTE ST 91405

Application / Permit
22010-20000-02846
Plan Check / Job No.
B22VN08863
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19' X 33' 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINERING.
Permit Issued
Issued on 9/25/2023
Issuing Office
Current Status
CofO Issued on 7/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 RAPHAEL ROSAS
Corrections Issued 7/11/2022 RAPHAEL ROSAS
Quality Review Completed 7/25/2022 STEVEN KIM
Building Plans Picked Up 7/28/2022 APPLICANT
Plan Check Approved 9/25/2023 RAPHAEL ROSAS
Issued 9/25/2023 APPLICANT
CofO in Progress 7/8/2024 VINCENT HANLEY
Permit Finaled 7/26/2024 RUBEN SALAS
CofO Issued 7/26/2024 RUBEN SALAS
Permit Finaled 7/26/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/20/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 7/25/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 7/25/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 10/3/2022 RIDWAN HARDY
Low Impact Development Cleared 9/19/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 9/20/2023 RYAN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 12/12/2023 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 12/12/2023 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 12/28/2023 Partial Approval JOHN COLEMAN
Wood Frame 12/28/2023 Partial Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 2/1/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved WILLIAM WREN
HVAC-Rough 2/12/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 2/12/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/21/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 2/21/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 2/21/2024 Partial Approval CRAIG DAVIS
Interior/Exterior Lathing 2/21/2024 Partial Approval CRAIG DAVIS
Verify Sprinkler Sign Off 2/21/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 2/23/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 2/23/2024 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 2/26/2024 Approved GREGG CUMMINGS
Green Building Rough 2/26/2024 Approved GREGG CUMMINGS
HVAC-Rough 2/26/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 2/26/2024 Not Ready for Inspection GREGG CUMMINGS
Insulation 2/28/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 3/6/2024 Approved DAVID MATSON
Interior/Exterior Lathing 3/6/2024 Partial Approval DAVID MATSON
Drywall Nailing 3/28/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 3/28/2024 Approved KIRK SANDERS
Final 6/7/2024 Corrections Issued VINCENT HANLEY
Green Building Final 6/7/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 6/7/2024 Corrections Issued VINCENT HANLEY
Smoke Detectors 6/7/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 7/3/2024 Approved VINCENT HANLEY
Final 7/3/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 7/3/2024 Approved VINCENT HANLEY
PLUMBING-Final 7/3/2024 Approved VINCENT HANLEY
Service/Power Release 7/3/2024 Approved VINCENT HANLEY