4213 N RHODES AVE 91604

Certificate Information: 4213 N RHODES AVE 91604

Application / Permit
22010-20000-02842
Plan Check / Job No.
B22VN14997
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 13'-0" X 18'-0" RECROOM WITH BATHROOM & SHOWER (EXTERIOR ACCESS ONLY) ACCESSORY TO THE MAIN DWELING.
Permit Issued
Issued on 11/29/2022
Issuing Office
Current Status
CofO Issued on 1/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 RAMA DABADGE
Corrections Issued 10/6/2022 RAMA DABADGE
Plan Check Approved 10/17/2022 RAHEL BEYENE
Issued 11/29/2022 APPLICANT
CofO in Progress 9/27/2023 CHRISTOPHE COCHRAN
Permit Finaled 1/22/2024 RUBEN SALAS
CofO Issued 1/22/2024 RUBEN SALAS
Permit Finaled 1/22/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/1/2022 ROMAN GUTIERREZ
Sewer availability Cleared 7/1/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 8/15/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/16/2022 ROMAN GUTIERREZ
ZI Cleared 8/19/2022 MIGUEL GAMBOA
Construction near power lines Cleared 9/9/2022 WALTER RAMIREZ

Contact Information

Contractor Nork Construction Inc; Lic. No.: 1058592-B 17204 CHATSWORTH ST #10      GRANADA HILLS, CA 91344
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/19/2022 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 12/27/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 3/10/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 3/10/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/17/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 3/17/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/20/2023 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/20/2023 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/20/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/30/2023 Partial Approval CHRISTOPHE COCHRAN
Insulation 4/5/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 4/11/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 5/8/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/22/2023 Approved JOHN COLEMAN
Final 9/18/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/18/2023 Approved CHRISTOPHE COCHRAN
Green Building Final 9/18/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 9/18/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 9/18/2023 Approved CHRISTOPHE COCHRAN
Final 9/27/2023 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 9/27/2023 Approved CHRISTOPHE COCHRAN
Service/Power Release 9/27/2023 Approved CHRISTOPHE COCHRAN