13437 N GLADSTONE AVE 91342
Certificate Information: 13437 N GLADSTONE AVE 91342
- Application / Permit
- 22010-20000-02812
- Plan Check / Job No.
- B22VN08678
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 29'-9" X 29'-6" ACCESSORY LIVING QUARTERS. WORK PER ENGINEER. NFPA-13D AUTOMATIC FIRE SPRINKLER SYSTEM REQUIRED. TYPE-VA CONSTRUCTION
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Valley
- Current Status
- Issued on 5/23/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2022 | ROSENDO MEDINA |
| Corrections Issued | 7/13/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 10/21/2022 | APPLICANT |
| Applicant returned to address corrections | 3/10/2023 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/27/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/16/2023 | DANIEL ABRAMYAN |
| Issued | 5/23/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | COLIN LOREDO |
| Low Impact Development | Cleared | 4/24/2023 | TOMMY YIN |
| Hydrant and Access approval | Cleared | 5/1/2023 | KURT CORRAL |
| Sewer availability | Cleared | 5/3/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/9/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/18/2023 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 8/2/2023 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/10/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Corrections Issued | KEVIN BERBERYAN |
| Special/Order Compliance | 10/2/2023 | Partial Inspection | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Wood Construction | 10/10/2023 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | No Access for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 1/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 1/8/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 1/18/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 1/18/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/18/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 2/12/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Wood Frame | 2/12/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/16/2024 | Approved | MICHEL ABAJAN |
| Insulation | 2/26/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/8/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 5/17/2024 | Partial Approval | KEVIN BERBERYAN |
| Gas Test | 6/25/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Sewer | 7/6/2024 | Partial Approval | ARUTYUN MADATYAN |
| Final | 12/24/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 4/22/2025 | Partial Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 4/22/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 4/22/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Final | 4/22/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 4/22/2025 | Not Required | KEVIN BERBERYAN |
| Smoke Detectors | 4/22/2025 | Approved | KEVIN BERBERYAN |
| Final | 4/29/2025 | Partial Inspection | KEVIN BERBERYAN |
| Green Building Final | 4/29/2025 | Approved | KEVIN BERBERYAN |
| Final | 6/13/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 11/6/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 11/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 11/17/2025 | Approved | KEVIN BERBERYAN |
| Final | 11/17/2025 | Not Ready for Inspection | KEVIN BERBERYAN |