15849 W BASSETT ST 91406
Certificate Information: 15849 W BASSETT ST 91406
- Application / Permit
- 22010-20000-02795
- Plan Check / Job No.
- B22VN08592
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 57'-6" X 32'-11" L-SHAPED ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Valley
- Current Status
- Issued on 6/6/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | ROSENDO MEDINA |
| Corrections Issued | 6/18/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| Plan Check Approved | 8/18/2022 | ROSENDO MEDINA |
| Issued | 6/6/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 6/27/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 8/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 8/4/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Just Go Green Incorporated; Lic. No.: 978128-B | 2010 WEST AVENUE K #247 LANCASTER, CA 93536 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/9/2023 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 7/13/2023 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 7/20/2023 | Corrections Issued | JUAN VALENZUELA |
| Sewer | 7/20/2023 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 7/20/2023 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/26/2023 | Conditional Approval | RAUL OLAGI |
| Special/Order Compliance | 7/26/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 9/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Partial Approval | THOMAS FINNILA |
| Gas Test | 9/20/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 9/25/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/27/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 9/27/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 9/27/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/27/2023 | Corrections Issued | RAUL OLAGI |
| Deputy Wood Construction | 10/20/2023 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/24/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 10/24/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/24/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 11/2/2023 | Approved | RAUL OLAGI |
| Insulation | 11/2/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 11/2/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 11/9/2023 | Approved | RAUL OLAGI |
| Insulation | 11/9/2023 | Approved | RAUL OLAGI |
| Shower Pan | 12/4/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/22/2024 | Corrections Issued | RAUL OLAGI |
| Final | 4/22/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 4/22/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 4/22/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 4/22/2024 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 4/22/2024 | Corrections Issued | RAUL OLAGI |