5225 N LINDLEY AVE 91356
Certificate Information: 5225 N LINDLEY AVE 91356
- Application / Permit
- 22010-20000-02786
- Plan Check / Job No.
- B22VN08575
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- eplan New Two Story Core and Shell medical Office. offsite parking is provided
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 7/28/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/28/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/21/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 2/5/2024 | ARSALAN SHABESTARI |
| Issued | 2/26/2024 | APPLICANT |
| TCO Issued (Expire Date: 06-03-2026) | 12/5/2025 | JEFFREY DURAN |
| CofO in Progress | 4/2/2026 | ROBERT DAVIS |
| Permit Finaled | 4/2/2026 | RICKEY JACKSON |
| CofO Issued | 4/2/2026 | RICKEY JACKSON |
| Permit Finaled | 4/2/2026 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/6/2022 | KURT CORRAL |
| Work Adjacent to Public Way | Cleared | 10/12/2022 | DAGOVERTO GUERRERO |
| Highway dedication | Cleared | 10/13/2022 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 10/17/2022 | NATHAN ROMINE |
| ZA Case | Cleared | 10/17/2022 | NATHAN ROMINE |
| Permit | Cleared | 10/19/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 10/27/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/27/2022 | RIDWAN HARDY |
| Green Code | Cleared | 11/4/2022 | Sella Benyamin |
| Frnt yard landscape/Water mgmt | Cleared | 11/9/2022 | NATHAN ROMINE |
| Prkng lot landscape/Water mgmt | Cleared | 11/10/2022 | NATHAN ROMINE |
| "D" conditions | Cleared | 11/15/2022 | NATHAN ROMINE |
| Specific Plan | Cleared | 11/15/2022 | NATHAN ROMINE |
| Low Impact Development | Cleared | 3/6/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 3/16/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/29/2023 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 3/29/2023 | BRANDON WILSON |
| Miscellaneous | Cleared | 4/28/2023 | NATHAN ROMINE |
| DAS Clearance | Cleared | 12/27/2023 | Sella Benyamin |
Contact Information
| Contractor | Vantage Development & Construction Corporation; Lic. No.: 955969-B | , |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/24/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/25/2024 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 4/25/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/26/2024 | Conditional Approval | ROBERT DAVIS |
| Piling/Pier/Caisson | 4/29/2024 | Partial Inspection | ROBERT DAVIS |
| Deputy Reinf. Masonry | 4/30/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 4/30/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/1/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/1/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/2/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/2/2024 | Approved | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/3/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/3/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/7/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/7/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/8/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/8/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/9/2024 | Approved | ROBERT DAVIS |
| Deputy Shotcrete | 5/9/2024 | Approved | ROBERT DAVIS |
| Masonry Wall/Backfill | 5/9/2024 | Partial Approval | ROBERT DAVIS |
| Reinforced Concrete Frame | 5/9/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Reinf. Masonry | 5/10/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/10/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/15/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 5/16/2024 | Conditional Approval | ROBERT DAVIS |
| Reinforced Concrete Frame | 5/16/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Shotcrete | 5/17/2024 | Approved | ROBERT DAVIS |
| Reinforced Concrete Frame | 5/17/2024 | Approved | ROBERT DAVIS |
| Deputy Shotcrete | 5/20/2024 | Conditional Approval | ROBERT DAVIS |
| Special/Order Compliance | 5/22/2024 | Partial Inspection | ROBERT DAVIS |
| Deputy Steel/Welding | 5/24/2024 | Conditional Approval | ROBERT DAVIS |
| Reinforced Concrete Frame | 5/24/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/3/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/5/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/10/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/11/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/12/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Shotcrete | 8/13/2024 | Conditional Approval | CAMERON CHABAN |
| Reinforced Concrete Frame | 8/13/2024 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 8/13/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Shotcrete | 8/16/2024 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 8/26/2024 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 8/26/2024 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 8/30/2024 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Conditional Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 9/26/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Structural Steel Frame | 9/26/2024 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 10/22/2024 | Partial Approval | BRIAN KELLY |
| Light Gage Steel Frame | 10/22/2024 | Partial Inspection | BRIAN KELLY |
| Deputy Reinf. Concrete | 10/25/2024 | No Result Entered | CAMERON CHABAN |
| Masonry Wall/Backfill | 10/29/2024 | Partial Approval | ROBERT DAVIS |
| Special/Order Compliance | 10/29/2024 | Corrections Issued | ROBERT DAVIS |
| Deputy Fireproofing | 10/30/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Fireproofing | 10/31/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Fireproofing | 11/1/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 11/14/2024 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 11/15/2024 | Approved | ROBERT DAVIS |
| Drywall Nailing | 11/15/2024 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 11/15/2024 | Partial Approval | ROBERT DAVIS |
| Structural Steel Frame | 11/15/2024 | Approved | ROBERT DAVIS |
| Deputy Fireproofing | 12/5/2024 | Conditional Approval | ROBERT DAVIS |
| Drywall Nailing | 12/10/2024 | Partial Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Not Ready for Inspection | ROBERT DAVIS |
| Interior/Exterior Lathing | 1/15/2025 | Partial Approval | ROBERT DAVIS |
| Insulation | 1/24/2025 | Partial Approval | ROBERT DAVIS |
| Special/Order Compliance | 4/3/2025 | Partial Inspection | ROBERT DAVIS |
| Special/Order Compliance | 7/28/2025 | Partial Inspection | ROBERT DAVIS |
| Final | 12/1/2025 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 12/1/2025 | Approved | ROBERT DAVIS |
| Green Building Final | 12/1/2025 | Approved | ROBERT DAVIS |
| Green Building Rough | 12/1/2025 | Approved | ROBERT DAVIS |
| Reinforced Masonry Frame | 12/1/2025 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 12/1/2025 | Approved | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 12/1/2025 | Approved | ROBERT DAVIS |
| Final | 4/2/2026 | OK to Issue CofO | ROBERT DAVIS |