9200 N WINNETKA AVE 91311
Certificate Information: 9200 N WINNETKA AVE 91311
- Application / Permit
- 22010-20000-02782
- Plan Check / Job No.
- B22VN08520
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ePLAN. GRADING FOR NEW UTILITIES.
- Permit Issued
- Issued on 7/20/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/6/2024
Permit Application Status History
| Submitted | 6/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/2/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 7/14/2022 | FARSHAD ALIMOHAMADI |
| Issued | 7/20/2022 | APPLICANT |
| Permit Finaled | 9/6/2024 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 6/23/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2022 | LEE GUILBEAUX |
| Metro Rail approval | Cleared | 7/13/2022 | FARSHAD ALIMOHAMADI |
| Miscellaneous | Cleared | 7/13/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Uncommon Builders Llc; Lic. No.: 1046026-B | , |
| Engineer | Larocca,, Francis; Lic. No.: C75121 | 2008A BELMONT LANE REDONDO BEACH, CA 90278 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 8/4/2022 | Partial Approval | BRIAN MILLER |
| Drainage Devices/Catch Basin | 8/4/2022 | Partial Approval | BRIAN MILLER |
| Sub-Drain | 8/4/2022 | Partial Approval | BRIAN MILLER |
| Fill/Backfill | 8/8/2022 | Corrections Issued | BRIAN MILLER |
| Bottom/Toe | 8/19/2022 | Partial Approval | BRIAN MILLER |
| Fill/Backfill | 8/19/2022 | Partial Approval | BRIAN MILLER |
| Sub-Drain | 8/19/2022 | Partial Approval | BRIAN MILLER |
| Initial Grading | 8/24/2022 | Approved | BRIAN MILLER |
| Bottom/Toe | 8/31/2022 | Partial Inspection | BRIAN MILLER |
| FLOOD-Proofing Certificate | 8/31/2022 | Partial Inspection | BRIAN MILLER |
| Rough | 8/31/2022 | Partial Inspection | BRIAN MILLER |
| Bottom/Toe | 9/13/2022 | Approved | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 9/13/2022 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 9/15/2022 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 9/26/2022 | Partial Approval | BRIAN MILLER |
| Sub-Drain | 10/26/2022 | Approved | VASIL MIHALEV |
| FLOOD-Proofing Certificate | 12/7/2022 | Approved | VASIL MIHALEV |
| Rough | 12/7/2022 | Approved | VASIL MIHALEV |
| Drainage Devices/Catch Basin | 12/21/2022 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 4/13/2023 | Partial Inspection | BRIAN MILLER |
| Excavation | 4/13/2023 | Partial Inspection | BRIAN MILLER |
| Irrigation/Landscape | 4/13/2023 | Partial Inspection | BRIAN MILLER |
| Drainage Devices/Catch Basin | 6/21/2023 | Partial Approval | MICHAEL TEMPLE |
| Fill/Backfill | 1/31/2024 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 9/6/2024 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |