11251 N KEWEN AVE 91340
Certificate Information: 11251 N KEWEN AVE 91340
- Application / Permit
- 22010-20000-02780
- Plan Check / Job No.
- B22VN08515
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 25' X 50' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2022 | SERGIO MUNIZ |
| Corrections Issued | 6/4/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| Applicant returned to address corrections | 11/7/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 11/21/2022 | MADISON ODELL |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 8/22/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/14/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 9/13/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 10/21/2022 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 11/2/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Builder'S Pathway Inc; Lic. No.: 1006297-B | 9728 VIA SIENA BURBANK, CA 91504 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 5/15/2024 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 5/15/2024 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/28/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/29/2024 | Partial Inspection | JENNIFER RABUCHIN |
| Wood Frame | 7/29/2024 | Partial Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/20/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/20/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 9/20/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/20/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 9/27/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/27/2024 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 10/4/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/21/2024 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/21/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 1/22/2025 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 2/4/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/20/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 6/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 6/20/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 6/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Final | 6/20/2025 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 6/20/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 6/20/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/6/2025 | Approved | MISAEL ESPARZA |
| Final | 8/6/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 8/6/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 8/6/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 8/6/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/6/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 8/6/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 8/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 8/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Final | 8/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 8/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Service/Power Release | 8/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 8/14/2025 | Approved | JENNIFER RABUCHIN |
| Final | 8/14/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/14/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/14/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/14/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 8/14/2025 | Approved | JENNIFER RABUCHIN |