17562-17564 W RAYMER ST 91325

Certificate Information: 17562-17564 W RAYMER ST 91325

Application / Permit
22010-20000-02746
Plan Check / Job No.
B22VN08424
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - NEW 1 STORY SFD (800 SF) PER SB9 CA GOV CODE 65852.21 AND ATTACHED ADU (800 SF) PER CA GOVT CODE 65852.2(E)(1)(A)
Permit Issued
Issued on 7/25/2023
Issuing Office
Current Status
CofO Issued on 10/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 STARR CHEN
Corrections Issued 7/7/2022 MONICA RAMIREZ
Quality Review Completed 7/8/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/15/2022 MONICA RAMIREZ
Plan Check Approved 7/25/2023 STARR CHEN
Issued 7/25/2023 APPLICANT
CofO in Progress 9/25/2025 NICHOLAS TROWBRIDGE
Permit Finaled 10/3/2025 RUBEN SALAS
CofO Issued 10/3/2025 RUBEN SALAS
Permit Finaled 10/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/2/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/2/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 3/2/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 3/29/2023 RUEL COLE
Low Impact Development Cleared 5/17/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 5/19/2023 DAGOVERTO GUERRERO
Senate Bill 9 Cleared 6/13/2023 STEVEN WECHSLER
Metro Rail approval Cleared 7/7/2023 JENNIFER SU

Contact Information

Contractor Markarian Setrag; Lic. No.: 832632-B       ,
Contractor Pampa Investment Inc; Lic. No.: 832632-B       ,
Engineer Moser,, Bradley Charles; Lic. No.: NA68803       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/15/2023 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/20/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 10/17/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 10/17/2023 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 10/17/2023 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 10/17/2023 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 10/17/2023 Not Ready for Inspection JAVIER RAMOS JR
Deputy Wood Construction 10/23/2023 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/25/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Approved JAVIER RAMOS JR
HVAC-Rough 10/25/2023 Approved JAVIER RAMOS JR
Insulation 10/25/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 10/25/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 10/25/2023 Approved JAVIER RAMOS JR
Drywall Nailing 10/30/2023 Partial Inspection JAVIER RAMOS JR
Insulation 10/30/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/30/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/26/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/26/2025 Partial Inspection JAVIER RAMOS JR
Final 2/26/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 2/26/2025 Corrections Issued JAVIER RAMOS JR
Gas Test 2/26/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 2/26/2025 Approved JAVIER RAMOS JR
Final 4/7/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 4/7/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Service/Power Release 4/7/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Final 5/29/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 5/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 6/4/2025 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 6/4/2025 Not Ready for Inspection DAVID ANDERSON
Service/Power Release 6/4/2025 Not Ready for Inspection DAVID ANDERSON
Final 6/12/2025 Conditional Approval NICHOLAS TROWBRIDGE
Footing/Foundation/Slab 6/12/2025 Approved NICHOLAS TROWBRIDGE
Service/Power Release 6/12/2025 Approved NICHOLAS TROWBRIDGE
Special/Order Compliance 6/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
Final 9/25/2025 OK to Issue CofO NICHOLAS TROWBRIDGE