8733 N MATILIJA AVE 91402
Certificate Information: 8733 N MATILIJA AVE 91402
- Application / Permit
- 22010-20000-02724
- Plan Check / Job No.
- B22VN08371
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/17/2023
- Issuing Office
- Current Status
- CofO Issued on 11/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2022 | DANIEL YIP |
| Corrections Issued | 6/5/2022 | DANIEL YIP |
| Quality Review Completed | 6/27/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/29/2022 | DANIEL YIP |
| Plan Check Approved | 10/10/2022 | DANIEL YIP |
| Issued | 7/17/2023 | APPLICANT |
| CofO in Progress | 11/8/2024 | GREGG CUMMINGS |
| Permit Finaled | 11/27/2024 | DANIEL ORRANTE |
| CofO Issued | 11/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 6/30/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 6/30/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 8/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 7/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/28/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 7/28/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/8/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 8/8/2023 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/24/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/10/2023 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 10/10/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/2/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 11/2/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 11/2/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/7/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/7/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 11/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/1/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/1/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/1/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 2/27/2024 | Approved | GREGG CUMMINGS |
| Insulation | 2/27/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 3/7/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/7/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 3/7/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/9/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/9/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 10/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 10/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 10/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 10/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/31/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 10/31/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/31/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 10/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 10/31/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/7/2024 | Approved | GREGG CUMMINGS |
| Final | 11/7/2024 | OK to Issue CofO | GREGG CUMMINGS |
| Service/Power Release | 11/7/2024 | Approved | GREGG CUMMINGS |