18940 W STRATHERN ST 91335
Certificate Information: 18940 W STRATHERN ST 91335
- Application / Permit
- 22010-20000-02716
- Plan Check / Job No.
- B22VN08301
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW DETACHED 1 STORY (24'-0"x60'-0"), 1363 SQFT STORAGE BUILDING AT REAR OF PROPERTY W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | PETER MOSESIAN |
| Corrections Issued | 6/5/2022 | PETER MOSESIAN |
| Quality Review Completed | 6/8/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/10/2022 | APPLICANT |
| Applicant returned to address corrections | 7/13/2022 | PETER MOSESIAN |
| Plan Check Approved | 9/27/2022 | PETER MOSESIAN |
| Issued | 10/3/2022 | APPLICANT |
| CofO in Progress | 11/3/2023 | JEFFREY BULL |
| No Progress | 11/15/2023 | JOHN JANSON |
| CofO in Progress | 12/21/2023 | JOHN JANSON |
| CofO Issued | 12/21/2023 | JOHN JANSON |
| Permit Finaled | 12/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZA Case | Cleared | 8/12/2022 | STEVEN WECHSLER |
| Hydrant and Access approval | Cleared | 9/12/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 9/13/2022 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/8/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 12/28/2022 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 12/28/2022 | Approved | JEFFREY BULL |
| Verify Sprinkler Sign Off | 12/28/2022 | Not Ready for Inspection | JEFFREY BULL |
| Wood Frame | 12/28/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/5/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 5/5/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 5/5/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/5/2023 | Approved | SEAN HAUPT |
| Underground Mechanical | 5/5/2023 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 5/5/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 11/3/2023 | Approved | JEFFREY BULL |
| Final | 11/3/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 11/3/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 11/3/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 11/3/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Required | JEFFREY BULL |
| Service/Power Release | 11/3/2023 | Not Required | JEFFREY BULL |
| Smoke Detectors | 11/3/2023 | Approved | JEFFREY BULL |
| Special/Order Compliance | 11/16/2023 | Corrections Issued | JEFFREY BULL |