7435 N BECK AVE 91605
Certificate Information: 7435 N BECK AVE 91605
- Application / Permit
- 22010-20000-02713
- Plan Check / Job No.
- B22VN08294
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE 21'-4"X39'-6" TWO STORY ACCESSORY DWELLING UNIT (PER LAMC 12.22 A.33(c) and (d)) WITH ATTACHED TWO CAR GARAGE. (SEE COMMENTS) *THE LID CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR LID REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY*
- Permit Issued
- Issued on 9/30/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | DAWN MC NULTY |
| Corrections Issued | 6/27/2022 | DAWN MC NULTY |
| Quality Review Completed | 6/29/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/3/2022 | APPLICANT |
| Applicant returned to address corrections | 9/26/2022 | DAWN MC NULTY |
| Plan Check Approved | 9/29/2022 | DAWN MC NULTY |
| Issued | 9/30/2022 | APPLICANT |
| CofO in Progress | 5/25/2023 | JENNIFER RABUCHIN |
| CofO Issued | 6/9/2023 | MICHAEL SMITH |
| Permit Finaled | 6/9/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/8/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/22/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 9/8/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/29/2022 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 10/5/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 10/19/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 12/12/2022 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 12/13/2022 | Conditional Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Corrections Issued | JOHN HAYES |
| Special/Order Compliance | 12/16/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 12/30/2022 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 12/30/2022 | Approved | JOHN COLEMAN |
| Green Building Rough | 12/30/2022 | Approved | JOHN COLEMAN |
| HVAC-Rough | 12/30/2022 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 12/30/2022 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 12/30/2022 | Approved | JOHN COLEMAN |
| Insulation | 1/4/2023 | Corrections Issued | JOHN HAYES |
| Masonry Wall/Backfill | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 1/11/2023 | Approved | JOHN HAYES |
| Shower Pan | 1/11/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 1/17/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/17/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 1/17/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/26/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 2/28/2023 | Partial Approval | JOHN HAYES |
| Sewer | 3/3/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 5/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 5/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 5/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/18/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 5/18/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 5/18/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| Final | 5/24/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/24/2023 | Approved | JENNIFER RABUCHIN |