20361 W HARTLAND ST 91306
Certificate Information: 20361 W HARTLAND ST 91306
- Application / Permit
- 22010-20000-02709
- Plan Check / Job No.
- B22VN08272
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. (SEE COMMENTS)
- Permit Issued
- Issued on 10/28/2024
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 6/1/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/6/2022 | APPLICANT |
| Plan Check Approved | 10/28/2024 | MOHAMMAD ESMAILI |
| Issued | 10/28/2024 | APPLICANT |
| CofO in Progress | 12/11/2025 | ROBERT GOLD |
| Permit Finaled | 12/12/2025 | JOHN JANSON |
| CofO Issued | 12/12/2025 | JOHN JANSON |
| Permit Finaled | 12/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/1/2022 | OSCAR CASTRO |
| Address approval | Cleared | 6/6/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 6/6/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 7/9/2022 | RUEL COLE |
| ZI | Cleared | 7/11/2022 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 12/20/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/23/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 12/23/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/26/2025 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 3/26/2025 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/3/2025 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/14/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Corrections Issued | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Approved | JUAN ALVARADO |
| Sewer | 4/30/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 5/16/2025 | Approved | ALEXANDER HANDY |
| Sewer | 5/16/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 5/16/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/27/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 5/27/2025 | Approved | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 5/27/2025 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 5/27/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 6/2/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 6/6/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 6/20/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/6/2025 | Partial Approval | ROBERT GOLD |
| Final | 11/6/2025 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 11/6/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV No Gas | ROBERT GOLD |
| Service/Power Release | 11/6/2025 | Not Required | ROBERT GOLD |
| Smoke Detectors | 11/6/2025 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 11/19/2025 | Approved | GEVORK IPCHYAN |
| Final | 11/19/2025 | OK to Issue CofO | GEVORK IPCHYAN |
| Smoke Detectors | 11/19/2025 | Approved | GEVORK IPCHYAN |