13866 W DAVENTRY ST 91331
Certificate Information: 13866 W DAVENTRY ST 91331
- Application / Permit
- 22010-20000-02684
- Plan Check / Job No.
- B22VN08155
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-6" X 23'-2" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER ENG.
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 6/2/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/6/2022 | APPLICANT |
| Applicant returned to address corrections | 9/12/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/4/2022 | MIROOSH KHACHATOORIAN |
| Issued | 10/17/2022 | APPLICANT |
| CofO in Progress | 7/28/2023 | MICHEL ABAJAN |
| CofO Issued | 9/11/2023 | RUBEN SALAS |
| Permit Finaled | 9/11/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 6/13/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 7/19/2022 | LAVEON RIDER |
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Purple Construction Inc; Lic. No.: 1020672-B | 308 S PALM AVE ALHAMBRA, CA 91803 |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 11/16/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 11/16/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/1/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 12/1/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 12/1/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/9/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/20/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 1/20/2023 | Approved | MISAEL ESPARZA |
| Insulation | 1/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 2/3/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/3/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/9/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/9/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/9/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/9/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/13/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/19/2023 | Approved | MICHEL ABAJAN |
| Final | 4/19/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/19/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/19/2023 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 4/19/2023 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 4/19/2023 | Approved | MICHEL ABAJAN |
| METHANE-Final | 4/19/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 4/19/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/19/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 4/19/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 4/19/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 4/19/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/15/2023 | Approved | MICHEL ABAJAN |
| Final | 5/15/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 5/15/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/15/2023 | Approved | MICHEL ABAJAN |
| Service/Power Release | 5/15/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/28/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 7/28/2023 | Approved | MICHEL ABAJAN |