1101 N MONUMENT ST 90272

Certificate Information: 1101 N MONUMENT ST 90272

Application / Permit
22010-20000-02683
Plan Check / Job No.
B22VN08146
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD (3692 SQFT) W/ATT 2-CAR GARAGE (322 SQFT), (63'-2"x37'-5") W/TRUSS PLANS AND DESIGN W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/31/2023
Issuing Office
Current Status
CofO Issued on 7/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 PETER MOSESIAN
Corrections Issued 6/5/2022 PETER MOSESIAN
Quality Review Completed 6/9/2022 OMID HEDAYAT
Building Plans Picked Up 6/10/2022 APPLICANT
Plan Check Approved 11/22/2022 PETER MOSESIAN
Issued 5/31/2023 APPLICANT
CofO in Progress 7/18/2024 ARAM AVEDISIAN
Permit Finaled 7/29/2024 DANIEL ORRANTE
CofO Issued 7/29/2024 DANIEL ORRANTE
Permit Finaled 7/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 6/8/2022 NELSON RODRIGUEZ
ZA Case Cleared 6/8/2022 NELSON RODRIGUEZ
ZA Case Cleared 6/8/2022 NELSON RODRIGUEZ
Permit Cleared 6/11/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 6/13/2022 SAUL GARCIA
Sewer availability Cleared 6/13/2022 SAUL GARCIA
Trees in Parkway Cleared 6/30/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 7/8/2022 LAVEON RIDER
Low Impact Development Cleared 11/9/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/10/2022 SAUL GARCIA
Grading Pre-Inspection Cleared 11/22/2022 PETER MOSESIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147
Engineer Zhao,, Xiaoming; Lic. No.: C70068 13402 PARK DR      CERRITOS, CA 90703

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2023 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 7/13/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/14/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/18/2023 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/18/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 8/18/2023 Partial Approval KEVIN SARGSYAN
Sewer 8/18/2023 Approved KEVIN SARGSYAN
Insulation 8/23/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/25/2023 Approved ARAM AVEDISIAN
Sewer 8/30/2023 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 10/10/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Corrections Issued OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/23/2023 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/30/2023 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/30/2023 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 11/1/2023 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 11/3/2023 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/6/2023 Approved ARAM AVEDISIAN
Green Building Rough 11/6/2023 Not Ready for Inspection ARAM AVEDISIAN
Verify Sprinkler Sign Off 11/6/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/15/2023 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 11/15/2023 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 11/15/2023 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 11/21/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/21/2023 Not Ready for Inspection ARAM AVEDISIAN
Insulation 11/29/2023 Approved KENNETH NAGLE
Shower Pan 11/29/2023 Approved KENNETH NAGLE
Insulation 12/1/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/1/2023 Partial Approval ARAM AVEDISIAN
Shower Pan 12/1/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/4/2023 Not Ready for Inspection ARAM AVEDISIAN
Drywall Nailing 12/6/2023 Approved ARAM AVEDISIAN
Green Building Rough 12/6/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/6/2023 Partial Approval ARAM AVEDISIAN
Pre-Inspection 2/29/2024 Partial Inspection ARAM AVEDISIAN
Underground Mechanical 3/20/2024 Partial Approval ARAM AVEDISIAN
Underground Mechanical 3/21/2024 Partial Approval ARAM AVEDISIAN
Gas Test 5/8/2024 No Access for Inspection KENNETH NAGLE
Gas Test 5/9/2024 Partial Approval KENNETH NAGLE
Gas Test 6/14/2024 Approved EVAN COOPER
PLUMBING-Final 6/14/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved EVAN COOPER
HVAC-Final 6/21/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 7/15/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 7/18/2024 Approved ARAM AVEDISIAN
Final 7/18/2024 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 7/18/2024 Approved ARAM AVEDISIAN
Service/Power Release 7/18/2024 Approved ARAM AVEDISIAN
Smoke Detectors 7/18/2024 Approved ARAM AVEDISIAN