10852 N PASO ROBLES AVE 91344

Certificate Information: 10852 N PASO ROBLES AVE 91344

Application / Permit
22010-20000-02669
Plan Check / Job No.
B22VN08091
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW 710 S.F. ADU to replace (e) 350 S.F garage
Permit Issued
Issued on 11/18/2022
Issuing Office
Current Status
CofO Issued on 6/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 MARCELA FRANQUEZ
Corrections Issued 6/30/2022 MARCELA FRANQUEZ
Quality Review Completed 7/8/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 7/26/2022 MARCELA FRANQUEZ
Plan Check Approved 11/4/2022 MARCELA FRANQUEZ
Issued 11/18/2022 APPLICANT
CofO in Progress 6/26/2023 STEVEN BACK
Permit Finaled 6/29/2023 JOHN JANSON
CofO Issued 6/29/2023 JOHN JANSON
Permit Finaled 6/29/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/11/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/12/2022 CARLOS AGUILERA
Sewer availability Cleared 7/12/2022 CARLOS AGUILERA
Low Impact Development Cleared 10/7/2022 ERNEST TSE
Construction near power lines Cleared 10/22/2022 RIDWAN HARDY
Construction within easement Cleared 10/22/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 11/3/2022 ROMAN GUTIERREZ

Contact Information

Contractor Ian Construction Inc; Lic. No.: 1025821-B 6578 SHELTONDALE AVE      WEST HILLS, CA 91307
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/19/2023 Not Ready for Inspection STEVEN BACK
Sewer 1/19/2023 Approved STEVEN BACK
Underground Mechanical 1/19/2023 Approved STEVEN BACK
Footing/Foundation/Slab 2/3/2023 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 2/9/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 3/7/2023 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved STEVEN BACK
Green Building Rough 3/7/2023 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 3/7/2023 Corrections Issued STEVEN BACK
Special/Order Compliance 3/8/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 4/6/2023 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 4/6/2023 Not Ready for Inspection STEVEN BACK
Gas Test 4/6/2023 Not Ready for Inspection STEVEN BACK
Green Building Rough 4/6/2023 Approved STEVEN BACK
HVAC-Rough 4/6/2023 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 4/6/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 4/6/2023 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 4/7/2023 Approved STEVEN BACK
ELECTRICAL-Rough 4/7/2023 Approved SEAN WIRCH
HVAC-Rough 4/7/2023 Approved STEVEN BACK
PLUMBING-Rough 4/7/2023 Approved STEVEN BACK
Insulation 4/11/2023 Approved STEVEN BACK
Drywall Nailing 4/17/2023 Approved STEVEN BACK
Interior/Exterior Lathing 4/17/2023 Approved STEVEN BACK
Shower Pan 4/17/2023 Approved JUSTIN HAWLEY
Final 6/13/2023 Corrections Issued STEVEN BACK
Green Building Final 6/13/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Approved STEVEN BACK
Smoke Detectors 6/13/2023 Approved STEVEN BACK
Final 6/20/2023 Corrections Issued HORACE FULTZ
Final 6/26/2023 OK to Issue CofO STEVEN BACK
Service/Power Release 6/26/2023 Approved STEVEN BACK