1220 1/4 S BERENDO ST 90006

Certificate Information: 1220 1/4 S BERENDO ST 90006

Application / Permit
22010-20000-02661
Plan Check / Job No.
B22VN08072
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ECPC: NEW 20'-0" x 35'-2" DETACHED ACCESSORY DWELLING UNIT. PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), AND (g). ALL WORK PER WFPP. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 2/13/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Corrections Issued 5/29/2022 LUISANGEL VALENZUELA
Assigned to Plan Check Engineer 5/30/2022 LUISANGEL VALENZUELA
Corrections Issued 6/27/2022 LUISANGEL VALENZUELA
Plan Check Approved 7/22/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 8/4/2022 APPLICANT
Issued 2/13/2024 APPLICANT
CofO in Progress 6/4/2024 ENRIQUE MIRELES
Permit Finaled 6/6/2024 DEROLD HAUFF
CofO Issued 6/6/2024 DEROLD HAUFF
Permit Finaled 6/6/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/2/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/3/2022 CELINA MORENO
Sewer availability Cleared 6/3/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 7/21/2022 CELINA MORENO

Contact Information

Contractor Sns Realty Inc; Lic. No.: 1113238-B 822 N MCCADDEN PL      LOS ANGELES, CA 90038

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/11/2024 Not Ready for Inspection ARTHUR NEGRETE
Underground Mechanical 3/11/2024 Partial Approval ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 3/15/2024 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 3/15/2024 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 3/18/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 4/4/2024 Approved ARTHUR NEGRETE
Green Building Rough 4/4/2024 Approved ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 4/4/2024 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 4/4/2024 Approved ARTHUR NEGRETE
Insulation 4/10/2024 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 4/10/2024 Partial Approval BRENDAN MORELLI
Drywall Nailing 4/16/2024 Approved JEFFREY MEAD
Final 5/20/2024 Corrections Issued WILLIAM KUEHN
Green Building Final 5/20/2024 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Approved WILLIAM KUEHN
Service/Power Release 5/20/2024 Not Required WILLIAM KUEHN
Smoke Detectors 5/20/2024 Approved WILLIAM KUEHN
Final 5/28/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 5/28/2024 Approved ENRIQUE MIRELES
Final 6/3/2024 OK to Issue CofO ENRIQUE MIRELES