10114-10116 N SILVERTON AVE 91042
Certificate Information: 10114-10116 N SILVERTON AVE 91042
- Application / Permit
- 22010-20000-02658
- Plan Check / Job No.
- B22VN08039
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CREATE 2- NEW DETACHED ADU-1 (1112 S,F.) , ADU-2 (1206 S,F.) AT THE REAR OF PROPERTY
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Current Status
- Issued on 5/10/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 7/13/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/14/2022 | GARO TELMI |
| Plan Check Approved | 5/3/2023 | ARSALAN SHABESTARI |
| Issued | 5/10/2023 | APPLICANT |
| Permit Expired-Status Void | 12/2/2024 | WILLIAM ROSE |
| Re-Activate Permit | 2/25/2025 | WILLIAM ROSE |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | COLIN LOREDO |
| Specific Plan | Cleared | 12/1/2022 | SARAH HOUNSELL |
| Low Impact Development | Cleared | 12/9/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 1/23/2023 | COLIN LOREDO |
| GPI Written Notices | Cleared | 5/3/2023 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 5/3/2023 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 12/2/2024 | No Access for Inspection | WILLIAM ROSE |
| PLUMBING-Rough | 8/15/2025 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 8/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 8/28/2025 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 9/8/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 10/20/2025 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 10/24/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/30/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 11/3/2025 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 11/5/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2025 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/16/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 3/16/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 3/16/2026 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 4/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 4/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 4/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 4/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 4/22/2026 | Partial Approval | NICHOLAS TROWBRIDGE |
| Shower Pan | 4/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 4/22/2026 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 4/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 4/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 5/4/2026 | Approved | NICHOLAS TROWBRIDGE |