10114-10116 N SILVERTON AVE 91042

Certificate Information: 10114-10116 N SILVERTON AVE 91042

Application / Permit
22010-20000-02658
Plan Check / Job No.
B22VN08039
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CREATE 2- NEW DETACHED ADU-1 (1112 S,F.) , ADU-2 (1206 S,F.) AT THE REAR OF PROPERTY
Permit Issued
Issued on 5/10/2023
Issuing Office
Current Status
Issued on 5/10/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 ARSALAN SHABESTARI
Corrections Issued 7/13/2022 ARSALAN SHABESTARI
Quality Review Completed 7/14/2022 GARO TELMI
Plan Check Approved 5/3/2023 ARSALAN SHABESTARI
Issued 5/10/2023 APPLICANT
Permit Expired-Status Void 12/2/2024 WILLIAM ROSE
Re-Activate Permit 2/25/2025 WILLIAM ROSE

Permit Application Clearance Information

Address approval Cleared 8/12/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/16/2022 COLIN LOREDO
Specific Plan Cleared 12/1/2022 SARAH HOUNSELL
Low Impact Development Cleared 12/9/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 12/12/2022 COLIN LOREDO
Sewer availability Cleared 1/23/2023 COLIN LOREDO
GPI Written Notices Cleared 5/3/2023 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 5/3/2023 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 12/2/2024 No Access for Inspection WILLIAM ROSE
PLUMBING-Rough 8/15/2025 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 8/28/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 8/28/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 9/8/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 10/20/2025 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 10/24/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/30/2025 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 11/3/2025 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 11/5/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 3/16/2026 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 3/16/2026 Corrections Issued NICHOLAS TROWBRIDGE
PLUMBING-Rough 3/16/2026 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 4/22/2026 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 4/22/2026 Approved NICHOLAS TROWBRIDGE
Green Building Rough 4/22/2026 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 4/22/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 4/22/2026 Partial Approval NICHOLAS TROWBRIDGE
Shower Pan 4/22/2026 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 4/22/2026 Approved NICHOLAS TROWBRIDGE
Insulation 4/27/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 4/27/2026 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 5/4/2026 Approved NICHOLAS TROWBRIDGE