115 S ROCKINGHAM AVE 90049

Certificate Information: 115 S ROCKINGHAM AVE 90049

Application / Permit
22010-20000-02641
Plan Check / Job No.
B22VN07969
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 114'6" X 69' TWO STORY SFD WITH ATTACHED THREE CAR GARAGE , NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 RARES BODEA
Corrections Issued 6/6/2022 RARES BODEA
Quality Review Completed 6/9/2022 STEVEN KIM
Building Plans Picked Up 6/9/2022 APPLICANT
Applicant returned to address corrections 9/22/2022 RARES BODEA
Plan Check Approved 12/9/2022 RARES BODEA
Issued 12/14/2022 APPLICANT
CofO in Progress 1/31/2025 ARAM AVEDISIAN
CofO Issued 2/6/2025 RICHARD STEINBACH
Permit Finaled 2/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/14/2022 DINAH GARIN
Permit Cleared 6/14/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/15/2022 DINAH GARIN
Sewer availability Cleared 6/15/2022 DINAH GARIN
Specific Plan Cleared 7/11/2022 FREDDY GARCIA
Hydrant and Access approval Cleared 7/25/2022 KURT CORRAL
Trees in Parkway Cleared 8/23/2022 ADALBERTO VERA
Low Impact Development Cleared 8/31/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/7/2022 DINAH GARIN
GPI Written Notices Cleared 9/22/2022 RARES BODEA
Grading Pre-Inspection Cleared 9/22/2022 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/27/2023 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 5/11/2023 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 5/12/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/16/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 9/22/2023 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 9/27/2023 Approved KEVIN SARGSYAN
Shower Pan 9/27/2023 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 10/19/2023 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved ARAM AVEDISIAN
HVAC-Rough 11/13/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/30/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 11/30/2023 Approved ARAM AVEDISIAN
Green Building Rough 11/30/2023 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 11/30/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/5/2023 Partial Approval ARAM AVEDISIAN
Insulation 12/15/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/18/2023 Partial Approval ARAM AVEDISIAN
Drywall Nailing 1/2/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/3/2024 Approved JESUS RODRIGUEZ
HVAC-Final 12/9/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 12/9/2024 Approved CARLOS MATAMOROS
Service/Power Release 12/9/2024 Approved KENNETH NAGLE
Final 1/31/2025 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 1/31/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/31/2025 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 1/31/2025 Approved ARAM AVEDISIAN