3522 S MCLAUGHLIN AVE 90066
Certificate Information: 3522 S MCLAUGHLIN AVE 90066
- Application / Permit
- 22010-20000-02640
- Plan Check / Job No.
- B22VN07968
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33' X 21' 4" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 6/19/2022 | GURUNATH NESARAJAH |
| Quality Review Completed | 6/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Applicant returned to address corrections | 11/18/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/23/2022 | GURUNATH NESARAJAH |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 7/17/2023 | JESUS PINEDA |
| No Progress | 7/25/2023 | DAVID FEILER |
| CofO in Progress | 8/24/2023 | DAVID FEILER |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
| CofO Issued | 9/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2022 | DINAH GARIN |
| ZI | Cleared | 7/8/2022 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2022 | DINAH GARIN |
| Sewer availability | Cleared | 7/13/2022 | DINAH GARIN |
| Specific Plan | Cleared | 8/18/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 10/24/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 12/23/2022 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 12/23/2022 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Pro Touch Construction Group; Lic. No.: 1054974-B | 17547 VENTURA BLVD #307A ENCINO, CA 91316 |
| Engineer | Samara,, Muzahim; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/21/2023 | Corrections Issued | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/28/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 3/2/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/8/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Conditional Approval | JOHNNY MIRANDA |
| Sewer | 3/17/2023 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 3/20/2023 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/28/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 3/28/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/28/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/3/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 4/3/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/3/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 4/3/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/3/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/7/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/12/2023 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/12/2023 | Approved | JOHNNY MIRANDA |
| Green Building Final | 6/12/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 6/12/2023 | Not Required | JOHNNY MIRANDA |
| Smoke Detectors | 6/12/2023 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 6/12/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/20/2023 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 7/14/2023 | Approved | JESUS PINEDA |
| Final | 7/14/2023 | OK to Issue CofO | JESUS PINEDA |
| HVAC-Final | 7/14/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 7/14/2023 | Approved | JESUS PINEDA |
| Service/Power Release | 7/14/2023 | Approved | JESUS PINEDA |
| Special/Order Compliance | 7/25/2023 | Corrections Issued | DAVID FEILER |