306 S ANITA AVE 90049

Certificate Information: 306 S ANITA AVE 90049

Application / Permit
22010-20000-02596
Plan Check / Job No.
B22VN07816
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 11/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 NILOOFAR MEHRAIN
Corrections Issued 6/7/2022 NILOOFAR MEHRAIN
Quality Review Completed 6/9/2022 STEVEN KIM
Building Plans Picked Up 6/10/2022 APPLICANT
Applicant returned to address corrections 10/18/2022 NILOOFAR MEHRAIN
Plan Check Approved 11/22/2022 NILOOFAR MEHRAIN
Issued 11/23/2022 APPLICANT
CofO in Progress 7/3/2025 HERBERT GIRON
Permit Finaled 7/8/2025 RICHARD STEINBACH
CofO Issued 7/8/2025 RICHARD STEINBACH
Permit Finaled 7/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 7/12/2022 EDUARDO HERMOSO
Trees in Parkway Cleared 7/13/2022 ADALBERTO VERA
Sewer availability Cleared 7/14/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 8/9/2022 JENSON LEE
Hydrant and Access approval Cleared 8/12/2022 KURT CORRAL
Address approval Cleared 8/16/2022 JENSON LEE
Permit Cleared 8/16/2022 JENSON LEE
Low Impact Development Cleared 9/16/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 10/5/2022 JENSON LEE
Excavation more than 5-ft deep Cleared 10/18/2022 CALOSHA APPROVED
GPI Written Notices Cleared 10/18/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/18/2022 NILOOFAR MEHRAIN

Contact Information

Contractor Merz Construction; Lic. No.: 775647-B 4808 LEMONA AVENUE      SHERMAN OAKS, CA 91403
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/14/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 7/6/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Shotcrete 7/6/2023 Partial Approval OGANES TARAKHCHYAN
Reinforced Concrete Frame 7/6/2023 Approved OGANES TARAKHCHYAN
Deputy Other (see comments) 7/10/2023 No Access for Inspection KENNETH NAGLE
Deputy Shotcrete 7/10/2023 No Access for Inspection KENNETH NAGLE
Underground Mechanical 7/25/2023 Partial Approval OGANES TARAKHCHYAN
Reinforced Masonry Frame 8/4/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/9/2023 Partial Approval OGANES TARAKHCHYAN
Masonry Wall/Backfill 8/14/2023 Partial Approval KEVIN SARGSYAN
Masonry Wall/Backfill 8/23/2023 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/28/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 9/1/2023 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 10/23/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 12/4/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Partial Approval ARAM AVEDISIAN
HVAC-Rough 1/2/2024 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 1/2/2024 Partial Approval KEVIN SARGSYAN
HVAC-Rough 1/22/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/31/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 1/31/2024 Corrections Issued ARAM AVEDISIAN
Green Building Rough 1/31/2024 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 1/31/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 2/1/2024 Approved ARAM AVEDISIAN
Insulation 4/2/2024 Conditional Approval ARAM AVEDISIAN
Shower Pan 4/2/2024 Approved ARAM AVEDISIAN
Insulation 4/3/2024 Approved ARAM AVEDISIAN
Drywall Nailing 4/15/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/16/2024 Partial Approval ARAM AVEDISIAN
Sewer 12/6/2024 Approved JESUS RODRIGUEZ
Gas Test 1/23/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/2/2025 Approved HERBERT GIRON
ELECTRICAL-Final 4/15/2025 Partial Approval MEL KHACHATOURIAN
Service/Power Release 5/22/2025 Approved KENNETH NAGLE
HVAC-Final 5/28/2025 Corrections Issued HERBERT GIRON
HVAC-Final 6/10/2025 Approved HERBERT GIRON
ELECTRICAL-Final 7/1/2025 Approved HERBERT GIRON
Final 7/1/2025 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 7/1/2025 Approved HERBERT GIRON
Green Building Final 7/1/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved HERBERT GIRON
Smoke Detectors 7/1/2025 Approved HERBERT GIRON
Final 7/3/2025 OK to Issue CofO HERBERT GIRON