7819 N CLEARFIELD AVE 91402
Certificate Information: 7819 N CLEARFIELD AVE 91402
- Application / Permit
- 22010-20000-02561
- Plan Check / Job No.
- B22VN07702
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 34' X 13' ACCESSORY DWELLING UNIT WITH ATTACHED 6' 10" X 4' 6" ATTACHED PORCH PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 5/21/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Applicant returned to address corrections | 8/15/2022 | YAQUB MIRZA |
| Applicant returned to address corrections | 9/26/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/14/2022 | GURUNATH NESARAJAH |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 12/8/2023 | DAVID MATSON |
| CofO in Progress | 12/8/2023 | DAVID MATSON |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/12/2022 | LAVEON RIDER |
| Sewer availability | Cleared | 7/12/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/29/2022 | AMMAR ELTAWIL |
| ZA Case | Cleared | 9/13/2022 | NATHAN ROMINE |
| Roof/Waste drainage to street | Cleared | 10/14/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 10/21/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 11/2/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/6/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/14/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/4/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/4/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/4/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 5/4/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 5/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 5/15/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 5/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 5/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 5/22/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/26/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 5/26/2023 | Approved | GREGG CUMMINGS |
| Wood Frame | 5/26/2023 | Partial Approval | GREGG CUMMINGS |
| Insulation | 6/2/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 6/8/2023 | Approved | DAVID MATSON |
| Green Building Rough | 6/8/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 6/8/2023 | Partial Approval | DAVID MATSON |
| Wood Frame | 6/8/2023 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 7/31/2023 | Approved | GREGG CUMMINGS |
| Final | 7/31/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 7/31/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 7/31/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 7/31/2023 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 7/31/2023 | Approved | GREGG CUMMINGS |
| Final | 11/14/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 11/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 11/27/2023 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 11/27/2023 | Approved | DAVID MATSON |