9015 S TOWNE AVE 90003
Certificate Information: 9015 S TOWNE AVE 90003
- Application / Permit
- 22010-20000-02537
- Plan Check / Job No.
- B22VN07664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN TO BUILD A (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/30/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 7/5/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/6/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/15/2022 | MOHAMMAD ESMAILI |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 9/20/2023 | MICHAEL LEWIS |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
| CofO Issued | 9/21/2023 | DEROLD HAUFF |
| Permit Finaled | 9/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/5/2022 | MARTIN FRAGOSO |
| Sewer availability | Cleared | 10/25/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | STEVE MELGAR |
| Address approval | Cleared | 10/31/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | STEVE MELGAR |
Contact Information
| Contractor | Teo'S Construction; Lic. No.: 778080-B | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/24/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 1/24/2023 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/26/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 2/17/2023 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/24/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 4/24/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/24/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/28/2023 | Conditional Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/28/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 4/28/2023 | Approved | MICHAEL LEWIS |
| Insulation | 5/3/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/3/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 5/12/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/30/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 5/30/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/12/2023 | Approved | MICHAEL LEWIS |
| Final | 7/12/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Gas Test | 7/12/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/12/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 7/12/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Smoke Detectors | 7/12/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/12/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 7/12/2023 | Approved | MICHAEL LEWIS |
| Final | 8/31/2023 | Corrections Issued | MICHAEL LEWIS |
| Service/Power Release | 8/31/2023 | Approved | MICHAEL LEWIS |
| Final | 9/18/2023 | OK to Issue CofO | MICHAEL LEWIS |
| Service/Power Release | 9/18/2023 | Approved | MICHAEL LEWIS |