9262 W THRUSH WAY 90069

Certificate Information: 9262 W THRUSH WAY 90069

Application / Permit
22010-20000-02521
Plan Check / Job No.
B22VN07616
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE W/ ROOFTOP DECK (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 4/14/2023
Issuing Office
Valley
Current Status
Issued on 4/14/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 NILOOFAR MEHRAIN
Corrections Issued 6/2/2022 NILOOFAR MEHRAIN
Quality Review Completed 6/2/2022 STEVEN KIM
Applicant returned to address corrections 9/29/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/27/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/9/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/13/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/19/2022 NILOOFAR MEHRAIN
Plan Check Approved 12/20/2022 NILOOFAR MEHRAIN
Issued 4/14/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/5/2022 JEANIE LAM
Address approval Cleared 7/6/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 7/6/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 7/6/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 7/6/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/6/2022 JEANIE LAM
Sewer availability Cleared 7/8/2022 JEANIE LAM
Trees in Parkway Cleared 7/15/2022 ADALBERTO VERA
Permit Cleared 7/25/2022 JEANIE LAM
BHO/Hillside ordinance Cleared 8/15/2022 JEANIE LAM
Hydrant and Access approval Cleared 8/25/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 11/17/2022 JEANIE LAM
GPI Written Notices Cleared 12/13/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/13/2022 NILOOFAR MEHRAIN
Disturb/Remove Protected Trees Cleared 4/5/2023 ADALBERTO VERA
Low Impact Development Cleared 4/10/2023 ROGELIO CORTES

Contact Information

Contractor J M A General Contractor; Lic. No.: 893018-B 5817 MCDONIE AVENUE      WOODLAND HILLS, CA 91367
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/17/2023 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/21/2023 Conditional Approval RAUL BARAJAS
Deputy Other (see comments) 7/25/2023 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 7/26/2023 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/27/2023 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/28/2023 Conditional Approval RAUL BARAJAS
Deputy Grading 8/2/2023 Conditional Approval RAUL BARAJAS
Deputy Grading 8/3/2023 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 8/3/2023 Not Ready for Inspection RAUL BARAJAS
Deputy Grading 8/4/2023 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/9/2023 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 8/9/2023 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/10/2023 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/11/2023 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/16/2023 Partial Inspection RAUL BARAJAS
Deputy Reinf. Concrete 8/21/2023 Conditional Approval FREDDIE RIVERA
Green Building Rough 8/22/2023 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 8/22/2023 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 8/22/2023 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 8/23/2023 Conditional Approval RAUL BARAJAS
Deputy Shotcrete 8/24/2023 Conditional Approval RAUL BARAJAS
Deputy Grading 9/5/2023 Conditional Approval RAUL BARAJAS
Deputy Grading 9/7/2023 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/20/2023 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 9/20/2023 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 9/22/2023 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 10/18/2023 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/1/2023 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 11/1/2023 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 11/2/2023 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 11/6/2023 Conditional Approval RAUL BARAJAS
Deputy Shotcrete 11/15/2023 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 11/15/2023 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 11/15/2023 Partial Approval RAUL BARAJAS
Deputy Shotcrete 11/17/2023 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/15/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 12/15/2023 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Inspection RAUL BARAJAS
Deputy Steel/Welding 1/11/2024 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/12/2024 Approved RAUL BARAJAS
PLUMBING-Rough 1/30/2024 Partial Approval STUART CHAPMAN
Underground Mechanical 1/30/2024 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 2/29/2024 Corrections Issued RAUL BARAJAS
Deputy Reinf. Concrete 3/1/2024 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/4/2024 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 3/6/2024 Conditional Approval RAUL BARAJAS
Masonry Wall/Backfill 3/8/2024 Partial Inspection ROY SPAULDING
Masonry Wall/Backfill 3/11/2024 Partial Approval RAUL BARAJAS
Masonry Wall/Backfill 3/13/2024 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 4/12/2024 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 4/16/2024 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 4/17/2024 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 5/8/2024 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Partial Approval RAUL BARAJAS
Deputy Wood Construction 5/22/2024 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval RAUL BARAJAS
Deputy Wood Construction 7/25/2024 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 8/12/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 8/12/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/12/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 8/14/2024 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 8/15/2024 Partial Approval RAUL BARAJAS
HVAC-Rough 8/15/2024 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 8/15/2024 Corrections Issued RAUL BARAJAS
HVAC-Rough 8/21/2024 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 8/21/2024 Partial Approval RAUL BARAJAS
Wood Frame 8/21/2024 Corrections Issued RAUL BARAJAS
Deputy Wood Construction 8/26/2024 Conditional Approval RAUL BARAJAS
HVAC-Rough 8/26/2024 Approved RAUL BARAJAS
PLUMBING-Rough 8/26/2024 Approved RAUL BARAJAS
Wood Frame 8/26/2024 Conditional Approval RAUL BARAJAS
Insulation 9/10/2024 Approved RAUL BARAJAS
Drywall Nailing 10/15/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 10/15/2024 Not Ready for Inspection RAUL BARAJAS
Shower Pan 10/23/2024 Partial Inspection RAUL BARAJAS
Shower Pan 10/25/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/19/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 12/5/2024 Approved RAUL BARAJAS
ELECTRICAL-Rough 1/23/2025 Not Ready for Inspection ROY SPAULDING
Sewer 8/13/2025 Corrections Issued BRENDAN MORELLI
Sewer 8/15/2025 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 2/12/2026 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/12/2026 Not Ready for Inspection CRAIG VAUGHAN
Final 2/12/2026 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/12/2026 Approved CRAIG VAUGHAN
Gas Test 2/12/2026 Approved CRAIG VAUGHAN
Green Building Final 2/12/2026 Approved CRAIG VAUGHAN
Green Building Rough 2/12/2026 Approved CRAIG VAUGHAN
HVAC-Final 2/12/2026 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 2/12/2026 Corrections Issued CRAIG VAUGHAN
Reinforced Concrete Frame 2/12/2026 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 2/12/2026 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 2/12/2026 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 2/12/2026 Approved CRAIG VAUGHAN
Final 2/25/2026 Corrections Issued DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Approved DAVID WILLIAMS
Service/Power Release 2/25/2026 Approved DAVID WILLIAMS
Smoke Detectors 2/25/2026 Approved DAVID WILLIAMS
Final 4/13/2026 Corrections Issued DAVID WILLIAMS
ELECTRICAL-Final 4/30/2026 Approved ROY SPAULDING
HVAC-Final 4/30/2026 Approved ROY SPAULDING
PLUMBING-Final 4/30/2026 Approved ROY SPAULDING